Project cost-quality-risk tradeoff analysis in a time-constrained problem

被引:53
作者
Mohammadipour, Faezeh [1 ]
Sadjadi, Seyed Jafar [1 ]
机构
[1] Iran Univ Sci & Technol, Dept Ind Engn, Tehran, Iran
关键词
Project scheduling; Cost increase; Risk enhancement; Quality reduction; Time constraint; Goal attainment; DISCRETE-TIME; OPTIMIZATION; MANAGEMENT; NETWORK; MODEL; UNCERTAINTY;
D O I
10.1016/j.cie.2016.02.025
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
One of the main issues in any scheduling of projects is the difficulty of convincing customer on total project makespan. There are many occasions where customer informs the contractor that the schedule must be shortened. This action could lead to increase in total cost as well as risk, which may also end of having lower quality project. This paper proposes a multi objective mixed integer linear programming for minimizing "project total extra cost", "project total risk enhancement" and "project total quality reduction" subject to time constraint. In other words, the proposed study provides a tradeoff between the three mentioned objectives to shorten the overall project duration. Goal attainment method is used for solving the multi objective model and obtaining the Pareto-optimal solutions. The computational experiments are also applied to evaluate the efficiency of the proposed model. (C) 2016 Published by Elsevier Ltd.
引用
收藏
页码:111 / 121
页数:11
相关论文
共 41 条
[1]  
Afhsar A., 2007, ASIAN J CIVIL ENG, V8, P113
[2]   Optimization of Project Time-Cost Trade-Off Problem with Discounted Cash Flows [J].
Ammar, Mohammad A. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2011, 137 (01) :65-71
[3]  
[Anonymous], 1991, Nonlinear Optimization, Complexity Issues
[4]  
[Anonymous], 1998, OPTIMIZATION MODELIN
[5]  
[Anonymous], 2013, Project management body of knowledge, VPMI
[6]   A multi-objective stochastic programming approach for supply chain design considering risk [J].
Azaron, A. ;
Brown, K. N. ;
Tarim, S. A. ;
Modarres, M. .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2008, 116 (01) :129-138
[7]   Time-cost trade-off via optimal control theory in Markov PERT networks [J].
Azaron, Amir ;
Katagiri, Hideki ;
Sakawa, Masatoshi .
ANNALS OF OPERATIONS RESEARCH, 2007, 150 (01) :47-64
[8]   A multi-objective discrete reliability optimization problem for dissimilar-unit standby systems [J].
Azaron, Amir ;
Katagiri, Hideki ;
Kato, Kosuke ;
Sakawa, Masatoshi .
OR SPECTRUM, 2007, 29 (02) :235-257
[9]   Modelling complex assemblies as a queueing network for lead time control [J].
Azaron, Amir ;
Katagiri, Hideki ;
Kato, Kosuke ;
Sakawa, Masatoshi .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2006, 174 (01) :150-168
[10]   Project management with time, cost, and quality considerations [J].
Babu, AJG ;
Suresh, N .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 88 (02) :320-327