Scheduling optimization under uncertainty - an alternative approach

被引:85
作者
Balasubramanian, J [1 ]
Grossmann, IE [1 ]
机构
[1] Carnegie Mellon Univ, Dept Chem Engn, Pittsburgh, PA 15213 USA
基金
美国国家科学基金会;
关键词
scheduling; uncertainty; fuzzy numbers; MILP models; tabu search; flowshop plants; new product development;
D O I
10.1016/S0098-1354(02)00221-1
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
The prevalent approach to the treatment of processing time uncertainties in production scheduling problems is through the use of probabilistic models. Apart from requiring detailed information about probability distribution functions, this approach also has the drawback that the computational expense of solving these models is very high. In this work, we present a non-probabilistic treatment of scheduling optimization under uncertainty, where we describe the imprecision and uncertainty in the task durations using concepts from fuzzy set theory. We first provide a brief review on the fuzzy set approach, comparing it with the probabilistic approach. We then present mixed integer linear programming (MILP) models derived from applying this approach to two different problems-flowshop scheduling and new product development process scheduling-and show how they can be used to predict most likely, optimistic and pessimistic values of metrics such as the makespan. Results indicate that these MILP models are computationally tractable for reasonably sized problems. We also describe tabu search implementations in order to handle larger problems. (C) 2002 Elsevier Science Ltd. All rights reserved.
引用
收藏
页码:469 / 490
页数:22
相关论文
共 48 条
[31]   EXACT SOLUTION OF THE NO-WAIT FLOWSHOP SCHEDULING PROBLEM WITH A COMPARISON TO HEURISTIC METHODS [J].
PEKNY, JF ;
MILLER, DL .
COMPUTERS & CHEMICAL ENGINEERING, 1991, 15 (11) :741-748
[32]   Multiperiod planning and scheduling of multiproduct batch plants under demand uncertainty [J].
Petkov, SB ;
Maranas, CD .
INDUSTRIAL & ENGINEERING CHEMISTRY RESEARCH, 1997, 36 (11) :4864-4881
[33]   An alternate MILP model for short-term scheduling of batch plants with preordering constraints [J].
Pinto, JM ;
Grossmann, IE .
INDUSTRIAL & ENGINEERING CHEMISTRY RESEARCH, 1996, 35 (01) :338-342
[34]   A CONTINUOUS-TIME MIXED-INTEGER LINEAR-PROGRAMMING MODEL FOR SHORT-TERM SCHEDULING OF MULTISTAGE BATCH PLANTS [J].
PINTO, JM ;
GROSSMANN, IE .
INDUSTRIAL & ENGINEERING CHEMISTRY RESEARCH, 1995, 34 (09) :3037-3051
[35]   A MIMO fuzzy model-based controller [J].
Postlethwaite, B ;
Edgar, C .
CHEMICAL ENGINEERING RESEARCH & DESIGN, 2000, 78 (A4) :557-564
[36]   COMPLETION TIMES IN SERIAL MIXED-STORAGE MULTIPRODUCT PROCESSES WITH TRANSFER AND SET-UP TIMES [J].
RAJAGOPALAN, D ;
KARIMI, IA .
COMPUTERS & CHEMICAL ENGINEERING, 1989, 13 (1-2) :175-186
[37]   Approximation of an ideal online scheduler for a multiproduct batch plant [J].
Sand, G ;
Engell, S ;
Märkert, A ;
Schultz, R ;
Schulz, C .
COMPUTERS & CHEMICAL ENGINEERING, 2000, 24 (2-7) :361-367
[38]  
SCHMIDT C, 1998, THESIS CARNEGIE MELL
[39]   The exact overall time distribution of a project with uncertain task durations [J].
Schmidt, CW ;
Grossmann, IE .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2000, 126 (03) :614-636
[40]   Optimization models for the scheduling of testing tasks in new product development [J].
Schmidt, CW ;
Grossmann, IE .
INDUSTRIAL & ENGINEERING CHEMISTRY RESEARCH, 1996, 35 (10) :3498-3510