Development of a DC current-blocking device for transformer neutrals

被引:84
作者
Bolduc, L
Granger, M
Paré, G
Saintonge, J
Brophy, L
机构
[1] Inst Rech Hydro Quebec, Varennes, PQ J3X 1S1, Canada
[2] Hydro Quebec, TransEnergie, Montreal, PQ H5B 1H7, Canada
[3] Hydro Quebec, TransEnergie, Montreal, PQ H2L 4M8, Canada
关键词
blocking capacitor; geomagnetically induced current (GIC); GIC blocking device; HVdc grounding electrode; neutral blocking/bypass device; neutral dc current-blocking device; transformer grounding;
D O I
10.1109/TPWRD.2004.835437
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
In the early 1990s, Hydro-Quebec undertook a joint project with GE to develop and commission a dc current-blocking series capacitor for the transmission lines forming part of its main power system in the area surrounding the grounding electrode of the Radisson HVdc substation. The aim of this project was to minimize the harmful effects of dc current flowing through the main network during the ground-return operating mode of the Radisson-Sandy Pond multiterminal HVdc link. With a view to having available technology applicable anywhere in the network, TransEnergie and IREQ, two divisions of Hydro-Quebec, later took part in the development of a dc current-blocking device that could be installed in transformer neutrals. This work was undertaken not only with immediate needs in mind but also to solve specific problems that could appear sporadically at different network locations. Tests on a prototype of the new blocking device were performed in the High Power Laboratory at IREQ, followed by tests on the preproduction unit, in accordance with the specified requirements. The neutral dc current-blocking device (NI BD) was then installed at a regional substation for a one-year operating period to verify its immunity under normal network events and switching conditions. During this period, no disruption to the smooth operation of the substation or protection of the ac system occurred. The NCBD operated correctly and suffered no fault or unsolicited operation.
引用
收藏
页码:163 / 168
页数:6
相关论文
共 19 条
[1]  
ALBERTSON VD, 1989, EFFECTS SOLKAR GEOMA, P47
[2]   Saturation time of transformers under dc excitation [J].
Bolduc, L ;
Gaudreau, A ;
Dutil, A .
ELECTRIC POWER SYSTEMS RESEARCH, 2000, 56 (02) :95-102
[3]   A study of geoelectromagnetic disturbances in Quebec, 2. Detailed analysis of a large event [J].
Bolduc, L ;
Langlois, P ;
Boteler, D ;
Pirjola, R .
IEEE TRANSACTIONS ON POWER DELIVERY, 2000, 15 (01) :272-278
[4]   Study of geoelectromagnetic disturbances in Quebec, 1. General results [J].
Bolduc, L ;
Langlois, P ;
Boteler, D ;
Pirjola, R .
IEEE TRANSACTIONS ON POWER DELIVERY, 1998, 13 (04) :1251-1256
[5]   GIC observations and studies in the Hydro-Quebec power system [J].
Bolduc, L .
JOURNAL OF ATMOSPHERIC AND SOLAR-TERRESTRIAL PHYSICS, 2002, 64 (16) :1793-1802
[6]  
BOLDUC L, 1990, T ENG OPERATING DIVI, V29
[7]  
BOLDUC L, 1977, ELECT POWER SYST RES, V1, P291
[8]  
*DEI DAIR EL IND, GIC BLOCK DEV DEI AP
[9]   ALTERNATIVES FOR BLOCKING DIRECT-CURRENT IN AC SYSTEM NEUTRALS AT THE RADISSON LG2 COMPLEX [J].
EITZMANN, MA ;
WALLING, RA ;
HUYNH, H ;
GRANGER, M ;
SUBLICH, M ;
KHAN, A ;
THANAWALA, HL ;
DUTIL, A ;
KAPPENMAN, JG .
IEEE TRANSACTIONS ON POWER DELIVERY, 1992, 7 (03) :1328-1337
[10]  
*EPRI, 1981, EL2020 EPRI INT ENG