Optimal crew routing for linear repetitive projects using graph theory

被引:25
作者
Gouda, Ahmed [1 ]
Hosny, Ossama [2 ]
Nassar, Khaled [2 ]
机构
[1] British Univ Egypt, Construct Engn Dept, Cairo, Egypt
[2] Amer Univ Cairo, Construct Engn Dept, Cairo, Egypt
关键词
Line-of-balance; Optimal crew route; Graph theory; Optimization model; Repetitive projects; Linear projects; CONSTRUCTION; OPTIMIZATION; CPM;
D O I
10.1016/j.autcon.2017.03.007
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The line-of-balance (LOB) technique is considered as an effective tool for planning and scheduling linear repetitive construction projects. One of the main assumptions of the LOB technique is the uniformity and constancy of production rate for an activity. Moreover, some aspects of the LOB technique can be modified in order to suit the nature of construction projects. This paper proposes a hybrid approach for scheduling linear projects that optimizes resource allocation using the LOB scheduling technique. The paper presents an optimization model for resolving resource constraint dilemmas in linear scheduling projects. The proposed model utilizes a Matrix Laboratory (MATLAB) code using graph theory as a searching algorithm to automate the model formulation. The novelty of the model is that it supports decision makers in formulating the optimal crews routing among various activities and also considering the allocation of multitasking skilled crews. A case study for a repetitive 4-km sewage pipeline installation is used to test the capabilities of the proposed model. Results show that the model can feasibly reduce the number of crews employed in linear repetitive construction projects. (C) 2017 Elsevier B.V. All rights reserved.
引用
收藏
页码:411 / 421
页数:11
相关论文
共 23 条
[1]  
Ammar M., 2002, P 3 MIDDL E REG CIV
[2]  
Ammar M. A., 2003, CONSTR MANAG ECON, V21, P535, DOI [10.1080/0144619032000073523, DOI 10.1080/0144619032000073523]
[3]   LOB and CPM Integrated Method for Scheduling Repetitive Projects [J].
Ammar, Mohammad A. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (01) :44-50
[4]  
Arditi D., 1987, P NORDNET INTERNET P
[5]  
Arditi D., 2002, Construction Management and Economics, V20, P353, DOI DOI 10.1080/01446190210131647
[6]   Multiskilled labor utilization strategies in construction [J].
Burleson, RC ;
Haas, CT ;
Tucker, RL ;
Stanley, A .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1998, 124 (06) :480-489
[7]  
Cross M., 1996, PROCESS ENG, V72, P51
[8]  
Gafy M., 2006, P JOINT INT C CONSTR
[9]   Cost optimization in projects with repetitive nonserial activities [J].
Hegazy, T ;
Wassef, N .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (03) :183-191
[10]  
Hegazy T., 1993, P AACE T MORG DEARB