Discrete-Element Analysis of the Excavation Performance of an EPB Shield TBM under Different Operating Conditions

被引:8
作者
Park, Byungkwan [1 ]
Lee, Chulho [2 ]
Choi, Soon-Wook [2 ]
Kang, Tae-Ho [2 ]
Chang, Soo-Ho [3 ]
机构
[1] Univ Sci & Technol UST, Civil & Environm Engn, Daejeon 34113, South Korea
[2] Korea Inst Civil Engn & Bldg Technol, Underground Space Safety Res Ctr, Goyang 10223, South Korea
[3] Korea Inst Civil Engn & Bldg Technol, Construct Ind Promot Dept, Goyang 10223, South Korea
来源
APPLIED SCIENCES-BASEL | 2021年 / 11卷 / 11期
关键词
EPB shield TBM; excavation performance; discrete element method; operating condition; NUMERICAL-SIMULATION; ROCK FRAGMENTATION; CUTTER WEAR; TUNNEL; MODEL; PREDICTION; MACHINE; ENERGY; FLOW;
D O I
10.3390/app11115119
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
This study used a discrete-element analysis to predict the excavation performance of a 7.73 m-diameter earth pressure balance (EPB) shield tunnel boring machine (TBM). The simulation mainly predicted several excavation performance indicators for the machine, under different operating conditions. The number of particles in the chamber and the chamber pressure varied, as the operating conditions changed during the simulated TBM excavation. The results showed that the compressive force, torque, and driving power acting on the TBM cutterhead varied with its rotation speed, increasing as the cutterhead rotation speed rose. The overall compressive force acting on all of the disc cutters and their impact wear increased linearly as the cutterhead rotation accelerated. The position of a disc cutter on the cutterhead had a particularly strong influence, with higher compressive forces experienced by the cutters closer to the center. In contrast, the gauge disc cutters at the transition zone of the cutterhead showed more wear than those elsewhere. The muck discharge rate and the driving power of the screw conveyor rose with increasing screw conveyor and cutterhead rotation speeds. Finally, this study suggests optimal operation conditions, based on pressure balance and operational management of the TBM.
引用
收藏
页数:24
相关论文
共 34 条
[1]   Investigating the effect of discontinuity geometrical parameters on the TBM performance in hard rock [J].
Afrasiabi, Navid ;
Rafiee, Ramin ;
Noroozi, Mehdi .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2019, 84 :326-333
[2]   Evaluation of tool wear in EPB tunneling of Tehran Metro, Line 7 Expansion [J].
Amoun, Sadegh ;
Sharifzadeh, Mostafa ;
Shahriar, Kourosh ;
Rostami, Jamal ;
Azali, Sadegh Tarigh .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2017, 61 :233-246
[3]  
Bejari H., 2011, MINING SCI TECHNOL C, V21, P507, DOI [10.1016/j.mstc.2011.06.008, DOI 10.1016/J.MSTC.2011.06.008]
[4]   DISCRETE NUMERICAL-MODEL FOR GRANULAR ASSEMBLIES [J].
CUNDALL, PA ;
STRACK, ODL .
GEOTECHNIQUE, 1979, 29 (01) :47-65
[5]  
DEM Solutions Ltd, 2019, EDEM 2019 US GUID
[6]   The performance of TBM disc cutter in soft strata: A numerical simulation using the three-dimensional RBD-DEM coupled method [J].
Fang, Yong ;
Yao, Zhigang ;
Xu, Wanghao ;
Tian, Qingfeng ;
He, Chuan ;
Liu, Sijin .
ENGINEERING FAILURE ANALYSIS, 2021, 119
[7]   Numerical study on the rock muck transfer process of TBM cutterhead with clump strategy based on discrete element method [J].
Geng, Qi ;
Zhang, Huijian ;
Liu, Xiaohui ;
Wang, Xuebin .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2019, 91
[8]   Disc cutting tests in Colorado red granite: Implications for TBM performance prediction [J].
Gertsch, R. ;
Gertsch, L. ;
Rostami, J. .
INTERNATIONAL JOURNAL OF ROCK MECHANICS AND MINING SCIENCES, 2007, 44 (02) :238-246
[9]   Numerical modelling of the effects of joint spacing on rock fragmentation by TBM cutters [J].
Gong, QM ;
Jiao, YY ;
Zhao, J .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2006, 21 (01) :46-55
[10]   Numerical modeling of the effects of joint orientation on rock fragmentation by TBM cutters [J].
Gong, QM ;
Zhao, J ;
Jiao, YY .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2005, 20 (02) :183-191