Particle swarm optimization-based schemes for resource-constrained project scheduling

被引:137
作者
Zhang, H [1 ]
Li, XD [1 ]
Li, H [1 ]
Huang, FL [1 ]
机构
[1] Hong Kong Polytech Univ, Dept Bldg & Real Estate, Hong Kong, Hong Kong, Peoples R China
关键词
particle swarm optimization; project scheduling; resource-constrained; priority-based representation; permutation-based representation;
D O I
10.1016/j.autcon.2004.08.006
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Particle swarm optimization (PSO) performed through particle flying along the trajectory that will be continuously updated is based to develop a solution-solving scheme for the resource-con strained project scheduling problem (RCPSP). The potential solution to the RCPSP in view of minimizing project duration is represented by the multidimensional particle, where two solution representations, i.e., priority-based representation and permutation-based representation, are respectively considered. The frameworks of the PSOs for the RCPSP according to the two solution representations are developed. Experimental analyses are presented to investigate the performance of the proposed PSO-based methodology, including comparison of the two representations and comparison with other approaches for the RCPSP. The study aims at providing an alternative means for the RCPSP by utilizing the features of PSO, such as particle-updating mechanism that may benefit from the searching experience of one particle itself or the best of all particles in the swarm. (C) 2004 Elsevier B.V. All rights reserved.
引用
收藏
页码:393 / 404
页数:12
相关论文
共 39 条
[1]   A robust genetic algorithm for resource allocation in project scheduling [J].
Alcaraz, J ;
Maroto, C .
ANNALS OF OPERATIONS RESEARCH, 2001, 102 (1-4) :83-109
[2]  
[Anonymous], 1989, GENETIC ALGORITHM SE
[3]  
Baar T., 1998, METAHEURISTICS ADV T, P1
[4]  
Bean J. C., 1994, ORSA Journal on Computing, V6, P154, DOI 10.1287/ijoc.6.2.154
[5]  
BELL CE, 1991, NAV RES LOG, V38, P315, DOI 10.1002/1520-6750(199106)38:3<315::AID-NAV3220380304>3.0.CO
[6]  
2-7
[7]   SOME EFFICIENT MULTI-HEURISTIC PROCEDURES FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING [J].
BOCTOR, FF .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1990, 49 (01) :3-13
[8]  
BOULEIMEN K, 1998, P 6 INT WORKSH PROJ, P19
[9]   Construction resource scheduling with genetic algorithms [J].
Chan, WT ;
Chua, DKH ;
Kannan, G .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (02) :125-132
[10]   COMPARISON OF HEURISTIC AND OPTIMUM SOLUTIONS IN RESOURCE-CONSTRAINED PROJECT SCHEDULING [J].
DAVIS, EW ;
PATTERSON, JH .
MANAGEMENT SCIENCE SERIES B-APPLICATION, 1975, 21 (08) :944-955