A full factory transient simulation model for the analysis of expected performance in a transition period

被引:11
作者
Klein, Moti [1 ]
Kalir, Adar [1 ]
机构
[1] Intel Corp, Qiriat Gat, Israel
来源
PROCEEDINGS OF THE 2006 WINTER SIMULATION CONFERENCE, VOLS 1-5 | 2006年
关键词
D O I
10.1109/WSC.2006.322963
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
Intel's Fab-18 is based in Israel, and has transitioned from producing 0.18-micron logic devices to producing 90nM flash products. During this transition period, the factory has de-ramped in volume of logic while ramping-up flash. AutoSched AP software was utilized for the development of a transient simulation model of the Fab's behavior during this period. It is the first attempt, at Intel, to utilize a full factory simulation in order to analyze and support decisions that pertain to a transient period of parallel de-ramp and ramp-up of technologies. Unlike typical simulation models for the analysis of factory performance and behavior in steady-state, the transient model poses several modeling challenges and requires major adjustments in dealing with these challenges. In this paper, we discuss those aspects. The benefits and contribution of such a model to decision making and the improvement of factory performance are also presented.
引用
收藏
页码:1836 / +
页数:2
相关论文
共 4 条
[1]  
ALLEN DE, 1999, P WINT SIM C 1999 DE
[2]  
DeJong CD, 2000, PROCEEDINGS OF THE 2000 WINTER SIMULATION CONFERENCE, VOLS 1 AND 2, P1505, DOI 10.1109/WSC.2000.899132
[3]  
Dümmler MA, 2000, PROCEEDINGS OF THE 2000 WINTER SIMULATION CONFERENCE, VOLS 1 AND 2, P1436
[4]  
KALIR A, 2001, SEM MAN OP MOD SIM S, P37