New results on the coordination of transportation and batching scheduling

被引:4
作者
Zhu, Hongli [1 ]
Leus, Roel [2 ]
Zhou, Hong [1 ]
机构
[1] Beihang Univ, Sch Econ & Management, Beijing 100191, Peoples R China
[2] Katholieke Univ Leuven, ORSTAT, Fac Econ & Business, B-3000 Leuven, Belgium
关键词
Scheduling; Transportation; Batching; NP-hardness; Strong NP-hardness; DETERIORATION; MACHINE;
D O I
10.1016/j.apm.2015.10.042
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
We study a planning problem to coordinate production and transportation scheduling, where a set of jobs needs to be transported from a holding area to a single batch machine for further processing. A number of results for this combined transportation-and-scheduling environment have recently been published. They look into the complexity status of the minimization of the sum of total processing time and processing cost, and of the sum of makespan and processing cost, for a fixed number of transporters. In this paper, we add to these results in that (1) we show that the earlier complexity results are still valid when the processing cost is removed from the objective, thus reducing to more "classic" scheduling objectives; (2) we assess the complexity status of the relevant problem variants with free number of transporters; and (3) we prove that the weighted-completion-time objective leads to an intractable problem even with a single transporter, contrary to the unweighted case. (C) 2015 Elsevier Inc. All rights reserved.
引用
收藏
页码:4016 / 4022
页数:7
相关论文
共 8 条
[1]  
[Anonymous], 1979, Computers and Intractablity: A Guide to the Theory of NP-Completeness
[2]  
Pinedo M.L., 2008, Scheduling: Theory, algorithms, and systems
[3]   A hybrid two-stage transportation and batch scheduling problem [J].
Tang, Lixin ;
Gong, Hua .
APPLIED MATHEMATICAL MODELLING, 2008, 32 (12) :2467-2479
[4]   Bicriteria Scheduling on a Single Batching Machine with Job Transportation and Deterioration Considerations [J].
Tang, Lixin ;
Gong, Hua ;
Liu, Jiyin ;
Li, Feng .
NAVAL RESEARCH LOGISTICS, 2014, 61 (04) :269-285
[5]   The coordination of transportation and batching scheduling [J].
Tang, Lixin ;
Gong, Hua .
APPLIED MATHEMATICAL MODELLING, 2009, 33 (10) :3854-3862
[6]   Flowshop scheduling problems with transportation or deterioration between the batching and single machines [J].
Tang, Lixin ;
Liu, Peng .
COMPUTERS & INDUSTRIAL ENGINEERING, 2009, 56 (04) :1289-1295
[7]   Two-machine flowshop scheduling problems involving a batching machine with transportation or deterioration consideration [J].
Tang, Lixin ;
Liu, Peng .
APPLIED MATHEMATICAL MODELLING, 2009, 33 (02) :1187-1199
[8]   A two stage scheduling with transportation and batching [J].
Zhu, Hongli .
INFORMATION PROCESSING LETTERS, 2012, 112 (19) :728-731