Mechanical response analysis of the buried pipeline due to adjacent foundation pit excavation

被引:94
作者
Zhang, Jie [1 ,2 ]
Xie, Rui [1 ]
Zhang, Han [1 ]
机构
[1] Southwest Petr Univ, Sch Mechatron Engn, Chengdu 610500, Sichuan, Peoples R China
[2] Xi An Jiao Tong Univ, State Key Lab Strength & Vibrat Mech Struct, Xian 710049, Shaanxi, Peoples R China
关键词
Buried pipeline; Foundation pit; FEM; Stress; Deformation; BARRIER; FAILURE; TUNNELS; SOILS;
D O I
10.1016/j.tust.2018.04.026
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Foundation pit is one of the most factors that threaten the safe operations of buried pipeline. In order to study the effect of foundation pit excavation on the buried pipeline, a three-dimensional model of pipeline and foundation pit was established, and the variation regulations of pipeline's deformation under the foundation pit excavation were investigated. Effects of pipeline parameters, foundation pit parameters, soil parameters and underground continuous wall on the stress, strain and deformation of the pipeline were studied. The results show that the underground continuous wall can effectively reduce the pipeline deformation. After the foundation pit excavation, the upper surface of the pipeline's middle section is pressed, and the lower surface is pulled, but the strain distribution of the pipeline at the edge of the pit is opposite. Horizontal and vertical displacements occurs on the pipeline, horizontal displacement moves to the inside of the pit, and vertical displacement moves to the bottom of the pit. The pipeline deformation decreases with the increasing of pipeline's radius-thickness ratio, but it increases with the increasing of the distance between the pipeline and foundation pit. The internal pressure has a small effect on the pipeline deformation. Pipeline deformation increases with increasing of the foundation pit's width and depth. However, the length of the foundation pit has no effect on the pipeline. The pipeline deformation increases with the soil's Poisson's ratio increases, and it decreases with the increasing of soil's cohesion and elastic modulus. With the increasing of thickness and elastic modulus of the underground continuous wall, the pipeline deformation decreases. Those results can be used for pipeline laying, construction, maintenance and safety evaluation.
引用
收藏
页码:135 / 145
页数:11
相关论文
共 20 条
[1]  
[Anonymous], 1969, P 7 INT C SOIL MECH
[2]  
[Anonymous], THESIS
[3]   Investigation of response of metro tunnels due to adjacent large excavation and protective measures in soft soils [J].
Chen, Renpeng ;
Meng, Fanyan ;
Li, Zhongchao ;
Ye, Yuehong ;
Ye, Junneng .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2016, 58 :224-235
[4]  
Ji K.Y., 2013, THESIS
[5]  
[姜峥 Jiang Zheng], 2014, [地下空间与工程学报, Chinese Journal of Underground Space and Engineering], V10, P362
[6]  
Kiar A., 2007, TUNNEL UNDERGR SPACE, V23, P431
[7]  
Li D.Y., 1999, Ind. Constr, V29, P36
[8]   Timoshenko beam solution for the response of existing tunnels because of tunneling underneath [J].
Li, Peng ;
Du, Shou-Ji ;
Shen, Shui-Long ;
Wang, Yan-Han ;
Zhao, Hong-Hua .
INTERNATIONAL JOURNAL FOR NUMERICAL AND ANALYTICAL METHODS IN GEOMECHANICS, 2016, 40 (05) :766-784
[9]   Centrifuge investigation into the effect of new shield tunnelling on an existing underlying large-diameter tunnel [J].
Li, Peng ;
Du, Shou-Ji ;
Ma, Xian-Feng ;
Yin, Zhen-Yu ;
Shen, Shui-Long .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2014, 42 :59-66
[10]   Calculation of head difference at two sides of a cut-off barrier during excavation dewatering [J].
Shen, Shui-Long ;
Wu, Yong-Xia ;
Misra, Anil .
COMPUTERS AND GEOTECHNICS, 2017, 91 :192-202