Optimizing the utilization of multiple labor shifts in construction projects

被引:27
作者
Jun, Dho Heon [1 ]
El-Rayes, Khaled [1 ]
机构
[1] Univ Illinois, Dept Civil & Environm Engn, Urbana, IL 61801 USA
关键词
Resource allocation; Acceleration; Labor; Shift work; Productivity; Scheduling; Genetic algorithms; COST TRADE-OFF; MULTIOBJECTIVE APPROACH; HIGHWAY CONSTRUCTION; GENETIC ALGORITHMS; OPTIMIZATION; MODEL; WORK; PRODUCTIVITY; GA;
D O I
10.1016/j.autcon.2009.12.015
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Evening and night shifts are often used in construction projects to accelerate schedules despite their negative impacts on construction cost and productivity. In order to minimize these negative impacts, this paper presents a multi-objective optimization model for scheduling multiple labor shifts in construction projects. The optimization model incorporates (1) an initialization module that initializes the scheduling optimization computations; (2) a scheduling module that develops practical multiple shift schedules and evaluates the impacts of decision variables on project performance; and (3) a multi-objective genetic algorithm module that searches for and identifies optimal/near optimal tradeoffs among minimizing project duration, reducing cost, and minimizing labor utilization in evening and night shifts. An application example is analyzed to illustrate the use of the model and demonstrate its capabilities in optimizing the planning and scheduling of multiple shifts in construction projects while complying with all job logic and labor availability constraints. Published by Elsevier B.V.
引用
收藏
页码:109 / 119
页数:11
相关论文
共 28 条
[1]  
Antill J.M., 1990, Critical path methods in construction practice, V3rd
[2]   ROTATING SHIFT WORK SCHEDULES THAT DISRUPT SLEEP ARE IMPROVED BY APPLYING CIRCADIAN PRINCIPLES [J].
CZEISLER, CA ;
MOOREEDE, MC ;
COLEMAN, RM .
SCIENCE, 1982, 217 (4558) :460-463
[3]  
Deb K., 2001, FAST ELITIST MULTIOB
[4]   Time-cost-quality trade-off analysis for highway construction [J].
El-Rayes, K ;
Kandil, A .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2005, 131 (04) :477-486
[5]   Optimum planning of highway construction under A+B bidding method [J].
El-Rayes, K .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (04) :261-269
[6]   Optimizing resource utilization for repetitive construction projects [J].
El-Rayes, K ;
Moselhi, O .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (01) :18-27
[7]   Using genetic algorithms to solve construction time-cost trade-off problems [J].
Feng, CW ;
Liu, LA ;
Burns, SA .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 1997, 11 (03) :184-189
[8]   Shift work, safety and productivity [J].
Folkard, S ;
Tucker, P .
OCCUPATIONAL MEDICINE-OXFORD, 2003, 53 (02) :95-101
[9]   Assignment and allocation optimization of partially multiskilled workforce [J].
Gomar, JE ;
Haas, CT ;
Morton, DP .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2002, 128 (02) :103-109
[10]  
GUERIN L, 2007, CREATE YOUR OWN EMPL