摘要
The aim of this paper is to propose efficient methods for solving the resource constrained project scheduling problem (RCPSP). These methods are based on makespan lower bounds, which linearly depend on the processing times of the activities. Linear lower bounds (LLB) can be obtained in different ways. The first application that we present is a general linear programming scheme for computing a makespan lower bound. The second application consists in associating redundant resources with LLB. Consequently we get new adjustments of release dates and tails of the project activities. These adjustments are tight for certain RCPSP instances, as shown by our computational results. (C) 2003 Published by Elsevier Science B.V.
引用
收藏
页码:314 / 324
页数:11
相关论文
共 50 条
  • [11] Resource-constrained project scheduling:: Computing lower bounds by solving minimum cut problems
    Möhring, RH
    Schulz, AS
    Stork, F
    Uetz, M
    ALGORITHMS - ESA'99, 1999, 1643 : 139 - 150
  • [12] An exact composite lower bound strategy for the resource-constrained project scheduling problem
    Coelho, Jose
    Vanhoucke, Mario
    COMPUTERS & OPERATIONS RESEARCH, 2018, 93 : 135 - 150
  • [13] A preemptive bound for the Resource Constrained Project Scheduling Problem
    Mohamed Haouari
    Anis Kooli
    Emmanuel Néron
    Jacques Carlier
    Journal of Scheduling, 2014, 17 : 237 - 248
  • [14] Genetic Algorithms for the Resource Constrained Project Scheduling Problem
    Gargiulo, F.
    Quagliarella, D.
    13TH IEEE INTERNATIONAL SYMPOSIUM ON COMPUTATIONAL INTELLIGENCE AND INFORMATICS (CINTI 2012), 2012, : 39 - 47
  • [15] A matheuristic for the resource-constrained project scheduling problem
    Vanhoucke, Mario
    Coelho, Jose
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2024, 319 (03) : 711 - 725
  • [16] A SURVEY ON THE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM
    OZDAMAR, L
    ULUSOY, G
    IIE TRANSACTIONS, 1995, 27 (05) : 574 - 586
  • [17] Resource-constrained project scheduling problem with reworking
    Liao Y.
    Lu Z.
    Jisuanji Jicheng Zhizao Xitong/Computer Integrated Manufacturing Systems, CIMS, 2019, 25 (11): : 2762 - 2774
  • [18] Extensions of the resource-constrained project scheduling problem
    Ding, Hongyan
    Zhuang, Cunbo
    Liu, Jianhua
    AUTOMATION IN CONSTRUCTION, 2023, 153
  • [19] A preemptive bound for the Resource Constrained Project Scheduling Problem
    Haouari, Mohamed
    Kooli, Anis
    Neron, Emmanuel
    Carlier, Jacques
    JOURNAL OF SCHEDULING, 2014, 17 (03) : 237 - 248
  • [20] Multidirectional Scheduling Scheme in Resource-Constrained Project Scheduling Problem
    Yoosefzadeh, Hamid R.
    Tareghian, Hamed R.
    Farahi, Mohammad H.
    NAVAL RESEARCH LOGISTICS, 2014, 61 (01) : 44 - 55