An adjustable robust optimization model for the resource-constrained project scheduling problem with uncertain activity durations

被引:102
作者
Bruni, M. E. [1 ]
Pugliese, L. Di Puglia [1 ]
Beraldi, P. [1 ]
Guerriero, F. [1 ]
机构
[1] Univ Calabria, Dept Mech Energy & Management Engn, I-87036 Arcavacata Di Rende, Italy
来源
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE | 2017年 / 71卷
关键词
Project scheduling; Resource constraints; Robust optimization; Benders decomposition; TABU SEARCH; CONSTRUCTION; STRATEGIES; STABILITY; PROGRAMS; DUALITY;
D O I
10.1016/j.omega.2016.09.009
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper addresses the resource-constrained project scheduling problem with uncertain activity durations. An adaptive robust optimization model is proposed to derive the resource allocation decisions that minimize the worst-case makespan, under general polyhedral uncertainty sets. The properties of the model are analyzed, assuming that the activity durations are subject to interval uncertainty where the level of robustness is controlled by a protection factor related to the risk aversion of the decision maker. A general decomposition approach is proposed to solve the robust counterpart of the resource-constrained project scheduling problem, further tailored to address the uncertainty set with the protection factor. An extensive computational study is presented on benchmark instances adapted from the PSPLIB. (C) 2016 Elsevier Ltd. All rights reserved.
引用
收藏
页码:66 / 84
页数:19
相关论文
共 66 条
[1]  
[Anonymous], 2001, THESIS TU BERLIN
[2]   MANAGING PROJECT ACTIVITY DURATION UNCERTAINTIES [J].
ARSHAM, H .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1993, 21 (01) :111-122
[3]   Insertion techniques for static and dynamic resource-constrained project scheduling [J].
Artigues, C ;
Michelon, P ;
Reusser, S .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2003, 149 (02) :249-267
[4]   Robust optimization for resource-constrained project scheduling with uncertain activity durations [J].
Artigues, Christian ;
Leus, Roel ;
Nobibon, Fabrice Talla .
FLEXIBLE SERVICES AND MANUFACTURING JOURNAL, 2013, 25 (1-2) :175-205
[5]   New competitive results for the stochastic resource-constrained project scheduling problem: exploring the benefits of pre-processing [J].
Ashtiani, Behzad ;
Leus, Roel ;
Aryanezhad, Mir-Bahador .
JOURNAL OF SCHEDULING, 2011, 14 (02) :157-171
[6]  
Balas E, 1971, APPL MATH PROGRAMMIN, P187
[7]  
Ballestin F, 2009, DECISION SCI, V38, P1
[8]   When it is worthwhile to work with the stochastic RCPSP? [J].
Ballestin, Francisco .
JOURNAL OF SCHEDULING, 2007, 10 (03) :153-166
[9]  
Bartusch M., 1988, Annals of Operations Research, V16, P201
[10]   Duality in robust optimization: Primal worst equals dual best [J].
Beck, Amir ;
Ben-Tal, Aharon .
OPERATIONS RESEARCH LETTERS, 2009, 37 (01) :1-6