THE EFFECT OF MANAGEMENT CONTROL ON LABOUR PRODUCTIVITY OF LABOUR-INTENSIVE WORKS IN GHANA

被引:2
|
作者
Bamfo-Agyei, Emmanuel [1 ]
Thwala, Didibhuku Wellington [2 ]
Aigbavboa, Clinton [3 ]
机构
[1] Cape Coast Tech Univ, Dept Bldg Technol, POB DL 50, Cape Coast, Ghana
[2] Univ South Africa UNISA, Coll Sci Engn & Technol, Dept Civil Engn, POB 392, Pretoria, South Africa
[3] Univ Johannesburg, Dept Construct Management & Quant Surveying, Auckland Pk,POB 524, Johannesburg, New Zealand
关键词
Construction industry; control; labour-intensive work; management; productivity; road construction; CONSTRUCTION; PROJECTS; SYSTEM;
D O I
10.18820/24150487/as29i1.1
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
In Ghana, many construction projects end in dispute, because contractors are unable to meet the completion time. As many construction operations are labour intensive, the question of labour productivity becomes paramount, especially as higher productivity levels usually translate into superior profitability, competitiveness, and income. This article aims to examine the management control factors affecting construction labour productivity in Ghanaian construction firms. It assesses the measuring techniques that are used to improve labour productivity in the construction firms. The article also determines the relationship between management control and labour productivity on labour-intensive works in Ghanaian construction firms. The study adopted a quantitative research design that used a questionnaire-based descriptive survey. Records available at the Ghana Social Opportunity Project (GSOP) indicate that 920 professionals are involved in labour-intensive works on road infrastructure. A purposive sampling technique was used to select 40 districts involved in road construction projects; 560 respondents were considered for the study. The summary of the data consisted of means, standard deviations, percentages, cross-tabulations, and frequencies. Principal axis factor analysis revealed three (3) components with eigenvalues above 1 that may influence labour productivity of labour-intensive works on road construction. These components are effective communication, supervision technique, and design inadequacies. Construction managers must monitor workforce performance by ensuring that the three factors influencing management control are considered.
引用
收藏
页码:1 / 25
页数:25
相关论文
共 23 条
  • [1] OPTIMISATION OF LABOUR-INTENSIVE PRODUCTIVITY FOR CONSTRUCTION PROJECTS IN GHANA
    Bamfo-Agyei, Emmanuel
    Thwala, Didibhuku Wellington
    Aigbavboa, Clinton
    ACTA STRUCTILIA, 2023, 30 (01) : 122 - 154
  • [2] Performance Improvement of Construction Workers to Achieve Better Productivity for Labour-Intensive Works
    Bamfo-Agyei, Emmanuel
    Thwala, Didibhuku Wellington
    Aigbavboa, Clinton
    BUILDINGS, 2022, 12 (10)
  • [3] Measuring Labour Productivity in Labour Intensive Works on the Road Construction in Ghana
    Bamfo-Agyei, Emmanuel
    Aigbavboa, Clinton
    Didibhuku, Thwala Welligton
    ADVANCES IN HUMAN FACTORS, SUSTAINABLE URBAN PLANNING AND INFRASTRUCTURE, 2019, 788 : 515 - 523
  • [4] Urban labour-intensive road construction in South Africa
    Gertzen D.
    Urban Forum, 1999, 10 (1) : 91 - 104
  • [5] Design and implementation of the Expanded Public Works Programme: Lessons from the Gundo Lashu labour-intensive programme
    Musekene, Eric Ndavheleseni
    DEVELOPMENT SOUTHERN AFRICA, 2015, 32 (06) : 745 - 757
  • [6] Labour-intensive construction sub-contractors: Their critical success factors
    Ng, S. Thomas
    Tang, Ziwei
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2010, 28 (07) : 732 - 740
  • [7] STRATEGIC MANAGEMENT AND LABOUR PRODUCTIVITY
    Zathurecky, Viliam
    SGEM 2016, BK 2: POLITICAL SCIENCES, LAW, FINANCE, ECONOMICS AND TOURISM CONFERENCE PROCEEDINGS, VOL IV, 2016, : 647 - 654
  • [8] The impact of a labour-intensive road construction programme in the Vhembe District, Limpopo Province
    Musekene, Eric Nndavheleseni
    DEVELOPMENT SOUTHERN AFRICA, 2013, 30 (03) : 332 - 346
  • [9] Labour productivity management: factors of growth, the role of social and labour monitoring
    Vertakova, Yuliya
    Maltseva, Irina
    Shulgina, Yuliya
    ECONOMIC ANNALS-XXI, 2019, 180 (11-12): : 173 - 182
  • [10] Use of the Labour-Intensive Method in the Repair of a Rural Road Serving an Indigenous Community in Jocotan (Guatemala)
    Ares, Rodrigo
    Fuentes, Jose-Maria
    Gallego, Eutiquio
    Ayuga, Francisco
    Garcia, Ana-Isabel
    SCIENCE AND ENGINEERING ETHICS, 2012, 18 (02) : 315 - 338