Theoretical development of stochastic delay analysis and forecast method

被引:5
作者
Yang, Jyh-Bin [1 ]
Teng, Ya-Ling [2 ]
机构
[1] Natl Cent Univ, Grad Inst Construct Engn & Management, Taoyuan, Taiwan
[2] Chung Hua Univ, Dept Construct Engn, Hsinchu, Taiwan
关键词
Delay analysis; stochastic approach; forecasting; construction project; FUZZY-LOGIC APPROACH; CONSTRUCTION PROJECTS; PROGRAM-EVALUATION; TECHNIQUE PERT; MODEL DELAYS; TIME; SIMULATION;
D O I
10.1080/02533839.2017.1336115
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Schedule delay analysis and claim management for construction projects have received much attention recently due to an increasing number of construction disputes. Most of the available delay analysis methods employ a deterministic approach that uses deterministic activity duration in as-planned schedules for schedule comparison. However, the duration of construction projects is naturally uncertain. Based on a mathematical-model delay analysis method, this study proposes an innovative approach, the Stochastic Delay Analysis and Forecast method (the SDAF method), which combines probabilistic activity duration and systematic delay analysis procedures to predict the contribution of a single activity's delay and its probability to cause overall project delay. This paper proposes a methodology and examines its results by means of a simulated case. Although this study has simplified practical problems, preliminary study results are valuable and form a basis for further research. Namely, these study results provide not only a stochastic delay analysis and forecast method but also a fundamental basis for developing advanced schedule delay analysis methodology to help in solving complicated schedule delay problems in construction projects.
引用
收藏
页码:391 / 400
页数:10
相关论文
共 27 条
[1]   A fuzzy logic approach to model delays in construction projects using translational models [J].
Al-Humaidi, H. M. ;
Tan, F. Hadipriono .
CIVIL ENGINEERING AND ENVIRONMENTAL SYSTEMS, 2010, 27 (04) :353-364
[2]   A fuzzy logic approach to model delays in construction projects using rotational fuzzy fault tree models [J].
Al-Humaidi, H. M. ;
Tan, F. Hadipriono .
CIVIL ENGINEERING AND ENVIRONMENTAL SYSTEMS, 2010, 27 (04) :329-351
[3]  
Alkass S., 1995, CONSTR MANAG ECON, V13, P335, DOI [DOI 10.1080/01446199500000038, 10.1080/01446199500000038]
[4]   Integrated Framework for Quantifying and Predicting Weather-Related Highway Construction Delays [J].
Apipattanavis, Somkiat ;
Sabol, Kevin ;
Molenaar, Keith R. ;
Rajagopalan, Balaji ;
Xi, Yunping ;
Blackard, Ben ;
Patil, Shekhar .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2010, 136 (11) :1160-1168
[5]   Selecting a delay analysis method in resolving construction claims [J].
Department of Civil and Architectural Engineering, Illinois Institute of Technology, Construction Engineering and Management Program, 3201 South Dearborn Street, Chicago, IL 60616, United States .
Int. J. Proj. Manage., 2006, 2 (145-155) :145-155
[6]   Integrated Approach to Overcome Shortcomings in Current Delay Analysis Practices [J].
Birgonul, M. Talat ;
Dikmen, Irem ;
Bektas, Sinasi .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2015, 141 (04)
[7]  
Callahan M.T., 1992, CONSTRUCTION PROJECT
[8]   Simplified program evaluation and review technique (PERT) [J].
Cottrell, WD .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1999, 125 (01) :16-22
[9]  
CRANDALL KC, 1976, J CONSTRUCT DIV-ASCE, V102, P415
[10]   Modified Time Impact Analysis Method [J].
Fan, Su-Ling .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2012, 138 (02) :227-233