Using the MD CAD model to develop the time-cost integrated schedule for construction projects

被引:35
作者
Feng, Chung-Wei [1 ]
Chen, Yi-Jao [2 ]
Huang, Jiun-Ru [3 ]
机构
[1] Natl Cheng Kung Univ, Dept Civil Engn, Tainan 70101, Taiwan
[2] Leader Univ, Dept Asset Sci, Tainan 70946, Taiwan
[3] Taiwan Construct Res Inst, Taipei 231, Taiwan
关键词
MD CAD model; Project scheduling; Genetic algorithms (GAs); MANAGEMENT;
D O I
10.1016/j.autcon.2009.12.009
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
daunting task for project planners to develop a time-cost integrated schedule due to the tremendous amount of information that need to be processed. Various research efforts have been made to develop model-based systems to facilitate information processing and integrate time and cost throughout the project life cycle. However, the results of the previous studies are not comprehensive enough to fulfill the requirements of project management. This paper presents a scheduling system that applies Multi-Dimensional (MD) CAD model, Object Sequencing Matrix (OSM), and genetic algorithms (GAs) to generate the time-cost integrated schedule for the construction project. A computer implementation called MD CAD model-based Project Scheduling System (MD_PSS) is also developed to verify the feasibility of the proposed approach. (C) 2009 Elsevier B.V. All rights reserved.
引用
收藏
页码:347 / 356
页数:10
相关论文
共 23 条
[1]   4D dynamic construction management and visualization software: 1. Development [J].
Chau, KW ;
Anson, M ;
Zhang, JP .
AUTOMATION IN CONSTRUCTION, 2005, 14 (04) :512-524
[2]   Development of automated communication of system for managing site information using internet technology [J].
Dawood, N ;
Akinsola, A ;
Hobbs, B .
AUTOMATION IN CONSTRUCTION, 2002, 11 (05) :557-572
[3]   Construction workspace planning: Assignment and analysis utilizing 4D visualization technologies [J].
Dawood, Nashwan ;
Mallasi, Zaki .
COMPUTER-AIDED CIVIL AND INFRASTRUCTURE ENGINEERING, 2006, 21 (07) :498-513
[4]   Generation of a construction planning from a 3D CAD model [J].
de Vries, Bauke ;
Harink, Jeroen M. J. .
AUTOMATION IN CONSTRUCTION, 2007, 16 (01) :13-18
[5]  
FENG CW, 2005, P 1 INT C CONSTR ENG, P515
[6]   Scheduling with computer-interpretable construction method models [J].
Fischer, MA ;
Aalami, F .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (04) :337-347
[7]  
Gen M., 1997, Genetic Algorithms and Engineering Design
[8]  
Gen M., 1999, GENETIC ALGORITHMS E, V7
[9]  
Golberg D. E., 1989, GENETIC ALGORITHMS S, V1989, P36
[10]  
Heesom D., 2004, CONSTR MANAG ECON, V22, P171, DOI [10.1080/0144619042000201376, DOI 10.1080/0144619042000201376]