Applying fuzzy method for measuring criticality in project network

被引:81
作者
Chen, Chen-Tung
Huang, Sue-Fen
机构
[1] Natl United Univ, Dept Informat Management, Miaoli 36003, Taiwan
[2] Da Yeh Univ, Dept Informat Management, Da Tsuen, Changhua, Taiwan
关键词
project management; fuzzy set; program evaluation and review technique (PERT); fuzzy PERT;
D O I
10.1016/j.ins.2007.01.035
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Program evaluation and review technique (PERT) is widely used as a tool for managing large-scale projects. In the traditional PERT model, the durations of activities (tasks) are either represented as crisp numbers or drawn from the beta distribution to estimate the task durations such as pessimistic, most likely and optimistic times. However, the operation time for each activity is usually difficult to define and estimate precisely in a real situation. The aim of this paper is to present an analytical method for measuring the criticality in a project network with fuzzy activity times. Triangular fuzzy numbers are used to express the operation times for all activities in a project network. A new model that combines fuzzy set theory with the PERT technique is proposed to determine the critical degrees of activities (tasks) and paths. In the proposed model, a possibility index is defined to identify the likelihood of meeting a specified required time for a project network. At the end of the paper, an example is presented to compare with those obtained using the proposed method as well as other methods. The comparisons reveal that the method proposed in this paper is more effective in determining the activity criticalities and finding the critical path. (c) 2007 Published by Elsevier Inc.
引用
收藏
页码:2448 / 2458
页数:11
相关论文
共 34 条
[1]  
[Anonymous], 1992, LECT NOTES ECON M, DOI DOI 10.1007/978-3-642-46768-4_5
[2]   A multi-objective resource allocation problem in PERT networks [J].
Azaron, A ;
Katagiri, H ;
Sakawa, M ;
Kato, K ;
Memariani, A .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2006, 172 (03) :838-854
[3]   A genetic algorithm approach for the time-cost trade-off in PERT networks [J].
Azaron, A ;
Perkgoz, C ;
Sakawa, M .
APPLIED MATHEMATICS AND COMPUTATION, 2005, 168 (02) :1317-1339
[4]   Critical path analysis in the network with fuzzy activity times [J].
Chanas, S ;
Zielinski, P .
FUZZY SETS AND SYSTEMS, 2001, 122 (02) :195-204
[5]   THE USE OF FUZZY VARIABLES IN PERT [J].
CHANAS, S ;
KAMBUROWSKI, J .
FUZZY SETS AND SYSTEMS, 1981, 5 (01) :11-19
[6]   Finding multiple possible critical paths using fuzzy PERT [J].
Chen, SM ;
Chang, TH .
IEEE TRANSACTIONS ON SYSTEMS MAN AND CYBERNETICS PART B-CYBERNETICS, 2001, 31 (06) :930-937
[7]  
Chiu C.W., 2002, INT J PROJECT MANAGE, V20, P561
[8]  
Dawson C. W., 1995, International Journal of Project Management, V13, P353, DOI 10.1016/0263-7863(95)00027-5
[9]  
Dawson R. J., 1998, International Journal of Project Management, V16, P299, DOI 10.1016/S0263-7863(97)00059-8
[10]   On latest starting times and floats in activity networks with ill-known durations [J].
Dubois, D ;
Fargier, H ;
Galvagnon, V .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2003, 147 (02) :266-280