A case study of modelling preventive maintenance of a production plant using subjective data

被引:10
作者
Christer, AH [1 ]
Wang, W
Sharp, J
Baker, R
机构
[1] Univ Salford, Ctr OR & Appl Stat, Salford M5 4WT, Lancs, England
[2] Eindhoven Univ Technol, NL-5600 MB Eindhoven, Netherlands
关键词
preventive maintenance; delay time concept; inspection; subjective data; estimation;
D O I
10.2307/3010470
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
In this paper we describe a subjective data based case study carried out at a company manufacturing copper products, which parallels a previously published objective data based study at the same plant. The purpose of this study is twofold. The first is to model the implementation of Planned Preventive Maintenance (PM) to an Extrusion Press using the delay time concept. The second is to test a method for estimation of model parameters from subjective data in the context of delay time modelling. The parameter values of the underlying fault arrival process and the delay time distribution were, unlike in a parallel objective study, initially estimated from subjective data obtained through a questionnaire survey. Since bias was present in the initial subjective estimate, a method of removing it was developed to improve the model fit. On the basis of the data analysis and delay time modelling, improved PM policy and procedures were proposed to increase the effectiveness and efficiency of PM.
引用
收藏
页码:210 / 219
页数:10
相关论文
共 12 条
[1]  
Baker R, 1991, IMA J MATH APPL BUSI, V3, P259
[2]   REVIEW OF DELAY-TIME OR MODELING OF ENGINEERING ASPECTS OF MAINTENANCE [J].
BAKER, RD ;
CHRISTER, AH .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1994, 73 (03) :407-422
[3]  
Christer A. H., 1995, IMA Journal of Mathematics Applied in Business and Industry, V6, P205, DOI 10.1093/imaman/6.2.205
[4]  
Christer A. H., 1995, IMA Journal of Mathematics Applied in Business and Industry, V6, P67, DOI 10.1093/imaman/6.1.67
[5]  
Christer A.H., 1990, IMA J MATH APPL BUSI, V2, P97
[6]   REDUCING PRODUCTION DOWNTIME USING DELAY-TIME ANALYSIS [J].
CHRISTER, AH ;
WALLER, WM .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1984, 35 (06) :499-512
[7]  
CHRISTER AH, 1984, J OPER RES SOC, V35, P401, DOI 10.1057/jors.1984.80
[8]  
CHRISTER AH, 1975, THEORY DECISION PRAC
[9]  
Hollander M., 1973, Nonparametric Statistical Methods
[10]  
Kendal M., 1979, ADV THEORY STAT, V2