Handling flexibility in a "generalised job shop" with a fuzzy approach

被引:8
作者
Allet, S [1 ]
机构
[1] Fac Polytech Mons, Serv Math & Rech Operat, B-7000 Mons, Belgium
关键词
scheduling problems; generalised job shop; fuzzy logic; flexible parameters; SEARCH ALGORITHMS;
D O I
10.1016/S0377-2217(02)00563-5
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
In this paper, we deal with a particular scheduling problem inspired by a practical case coming from a Belgian Pharmaceutical Company. This problem has some particularities with respect to the 'classical job shop problem'. The principal one is the existence of a delay between the end of an operation and the start of the next operation of the same job. This delay is not fixed but belongs generally to an interval range of possible values. A resolution method (the horizon method) has been proposed in the deterministic case (fixed data and strict constraints). In this method, the horizon time of each machine is discretised by unit times and at each unit time a binary value is associated; all the operations applied on the machines horizons are logic operations (OR, AND, right or left shifting and so on). Unfortunately, this method does not take into account several aspects of the problem: the existence of a preference relation on the possible values of the delay between successive operations and of flexible due dates. In this work, we modelise such flexible parameters using the fuzzy logic. We propose a new method generalizing the horizon method. This new method try to find (for the realisation of the jobs) a compromise between the choice of good values for the delay between couples of successive operations of the same job and good values for the completion time of the jobs. (C) 2002 Elsevier Science B.V. All rights reserved.
引用
收藏
页码:312 / 333
页数:22
相关论文
共 28 条
  • [1] AARTS EHL, 1988, SIMULATED ANNELING T
  • [2] AARTS EHL, 1993, WILEY INTERSCIENCE S
  • [3] [Anonymous], FUZZY SETS FUZZY LOG
  • [4] BLOCH C, 2002, IN PRESS APPL METAHE
  • [5] CHRETIENNE P, 1995, SCHEDULING THEORY
  • [6] Dell'Amico M., 1993, Annals of Operations Research, V41, P231, DOI 10.1007/BF02023076
  • [7] FUZZY CONSTRAINTS IN JOB-SHOP SCHEDULING
    DUBOIS, D
    FARGIER, H
    PRADE, H
    [J]. JOURNAL OF INTELLIGENT MANUFACTURING, 1995, 6 (04) : 215 - 234
  • [8] FARGIER H, 2001, ENG APPL ARTIF INTEL, P1
  • [9] Jobshop scheduling with imprecise durations: A fuzzy approach
    Fortemps, P
    [J]. IEEE TRANSACTIONS ON FUZZY SYSTEMS, 1997, 5 (04) : 557 - 569
  • [10] Garey M. R., 1979, Computers and intractability. A guide to the theory of NP-completeness