PREDESIGN COST ESTIMATION OF URBAN RAILWAY PROJECTS WITH PARAMETRIC MODELING

被引:40
作者
Sonmez, Rifat [1 ]
Ontepeli, Bahadir [2 ]
机构
[1] Middle E Tech Univ, Dept Civil Engn, TR-06531 Ankara, Turkey
[2] Renaissance Construct, TR-06540 Ankara, Turkey
关键词
predesign cost estimation; urban railway projects; regression analysis; neural networks; NEURAL-NETWORKS; BUILDINGS;
D O I
10.3846/1392-3730.2009.15.405-409
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper presents a parametric modeling method for predesign cost estimation of urban railway systems. Data of 13 light rail and metro projects located in Turkey were compiled for quantification of the impacts of parameters on the project costs. Parametric models have been developed using regression analysis and neural networks techniques. Ten linear regression models were used for determination of the parameters significantly impacting cost of urban railway projects. Two neural networks were considered as an alternative to regression models, particularly for the identification of the non-linear relations. Predictive behaviour and performance of the models were compared to determine a model that presents adequate relations and has a reasonable accuracy. The proposed method provides a powerful approach for determination of a satisfactory parametric cost model during early project stages by incorporating a coordinated use of regression analysis and neural network techniques.
引用
收藏
页码:405 / 409
页数:5
相关论文
共 11 条
[1]  
[Anonymous], 1988, Parallel distributed processing
[2]  
[Anonymous], 1997, COST EST CLASS SYST
[3]  
*EUR RAIL RES ADV, 2004, LIGHT RAIL METR SYST
[4]  
Gunaydin H. M., 2004, International Journal of Project Management, V22, P595, DOI 10.1016/j.ijproman.2004.04.002
[5]   Neural network model for parametric cost estimation of highway projects [J].
Hegazy, T ;
Ayed, A .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1998, 124 (03) :210-218
[6]   PREDESIGN COST ESTIMATING METHOD FOR MULTISTORY BUILDINGS [J].
KARSHENAS, S .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1984, 110 (01) :79-86
[7]   Hybrid models of neural networks and genetic algorithms for predicting preliminary cost estimates [J].
Kim, GH ;
Seo, DS ;
Kang, KI .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2005, 19 (02) :208-211
[8]  
KOUSKOULAS V, 1974, J CONSTRUCT DIV-ASCE, V100, P589
[9]  
ONTEPELI MB, 2005, THESIS MIDDLE E TU A
[10]   Conceptual cost estimation of building projects with regression analysis and neural networks [J].
Sonmez, R .
CANADIAN JOURNAL OF CIVIL ENGINEERING, 2004, 31 (04) :677-683