Study on Identifying Significant Risk Sources during Bridge Construction Based on Grey Entropy Correlation Analysis Method

被引:10
作者
Wang, Kunpeng [1 ]
Lu, Chenggang [1 ]
Li, Qingfu [2 ]
机构
[1] Powerchina Roadbridge Grp Co td, Beijing 100048, Peoples R China
[2] Zhengzhou Univ, Sch Water Conservancy Engn, Zhengzhou 450001, Peoples R China
关键词
MODEL;
D O I
10.1155/2021/6618039
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Nowadays, many methods have been used in the identification of bridge risk sources, and certain results have been achieved. However, the research on the identification of significant risk sources of bridges during the construction period is relatively weak, and these methods still have some defects, such as the correlation between risk sources is not considered comprehensively, the dynamic risk sources are not fully considered, and the weight assignment is highly subjective. In order to solve these problems, this paper comprehensively uses the combination of expert scoring method, fuzzy analytic hierarchy process (F-AHP), and grey entropy correlation analysis (GECA) to identify significant risk sources during bridge construction. Firstly, the F-AHP and expert scoring method are used to initially identify safety sources during the bridge construction period, which effectively considers the identification of dynamic risk sources. Secondly, the combination of the GRA method and EW method is applied to identify the significant risk sources during bridge construction period, which can effectively analyze the interrelationship between different factors and greatly reduce the interference of subjective factors in the weight assignment, so as to effectively control the risks in construction and protect the health of the bridge structure and property losses. Finally, the feasibility and rationality of the proposed method were verified by comparing the AHP and GECA proposed in this paper in combination with specific engineering examples, which provides a reference basis for the identification of significant risk sources during the follow-up bridge construction period.
引用
收藏
页数:15
相关论文
共 40 条
[1]   COMPREHENSIVE RISK MANAGEMENT USING FUZZY FMEA AND MCDA TECHNIQUES IN HIGHWAY CONSTRUCTION PROJECTS [J].
Ahmadi, Mohsen ;
Behzadian, Kourosh ;
Ardeshir, Abdollah ;
Kapelan, Zoran .
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2017, 23 (02) :300-310
[2]  
Bao L.S., 2009, J. Shenyang Jianzhu Univ. Soc. Sci, V25, P663, DOI CNKI:SUN:SYJZ.0.2009-04-010
[3]   Water resistance and a comprehensive evaluation model of magnesium oxychloride cement concrete based on Taguchi and entropy weight method [J].
Gong, Wei ;
Wang, Nan ;
Zhang, Na ;
Han, Wenliang ;
Qiao, Hongxia .
CONSTRUCTION AND BUILDING MATERIALS, 2020, 260
[4]  
Jin J., 2019, RES VALUE EVALUATION
[5]  
Li Q., 2019, FUZZY EVALUATION PAT
[6]  
Li Q.F., 2013, RES J APPL SCI ENG T, V6, P1523
[7]  
Li W.Q, 2016, CHINA WATER TRANSPOR, V16, P199
[8]  
Liang Z.J, 2017, PORT EC, V23, P58
[9]  
Lin X., 2006, RISK MANAGEMENT RES
[10]  
Liu M.Y, 2017, J CIV ENG MANAG, V34, P5