Enhanced lower bounds and exact procedures for total completion time minimization in a two-machine permutation flowshop with release dates

被引:4
作者
Mrad, Mehdi [1 ]
Chalghoumi, Sabrine [2 ]
Ladhari, Talel [2 ,3 ,4 ]
Gharbi, Anis [1 ]
机构
[1] King Saud Univ, Dept Ind Engn, Riyadh, Saudi Arabia
[2] Univ Tunis, BADEM, Tunis 2059, Tunisia
[3] Univ Tunis, Ecole Super Sci Econ & Commerciales Tunis, 1089 Montfleury, Tunis, Tunisia
[4] Umm Al Qura Univ, Coll Business Management, Dept Business Adm, Mecca, Saudi Arabia
关键词
flowshop; total completion time; release date; lower bounds; mixed-integer linear programming; INTEGER PROGRAMMING FORMULATIONS; SHOP SCHEDULING PROBLEM; LOCAL SEARCH; ALGORITHM;
D O I
10.1111/itor.12421
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
We consider the problem of minimizing the sum of completion times in a two-machine permutation flowshop subject to release dates. New procedures are proposed for effectively bounding the completion time of a given job that is processed at a given position. New assignment-based lower bounds are derived as well as an enhanced mathematical programming formulation. Our computational analysis shows a consistent tightness of the proposed lower bounds and a high outperformance of the enhanced mathematical formulation with respect to the classical one.
引用
收藏
页码:2432 / 2449
页数:18
相关论文
共 37 条
[1]  
AHMADI RH, 1990, NAV RES LOG, V37, P967, DOI 10.1002/1520-6750(199012)37:6<967::AID-NAV3220370616>3.0.CO
[2]  
2-K
[3]   The two-machine flowshop total completion time problem: Improved lower bounds and a branch-and-bound algorithm [J].
Akkan, C ;
Karabati, S .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2004, 159 (02) :420-429
[4]   Asymptotic analysis of online algorithms and improved scheme for the flow shop scheduling problem with release dates [J].
Bai, Danyu .
INTERNATIONAL JOURNAL OF SYSTEMS SCIENCE, 2015, 46 (11) :1994-2005
[5]  
Cayirli T, 2003, PROD OPER MANAG, V12, P519, DOI 10.1111/j.1937-5956.2003.tb00218.x
[6]   Two-machine flow shop scheduling with deteriorating jobs: minimizing the weighted sum of makespan and total completion time [J].
Cheng, Mingbao ;
Tadikamalla, Pandu R. ;
Shang, Jennifer ;
Zhang, Bixi .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2015, 66 (05) :709-719
[7]  
CHU CB, 1992, NAV RES LOG, V39, P859, DOI 10.1002/1520-6750(199210)39:6<859::AID-NAV3220390610>3.0.CO
[8]  
2-W
[9]   A simulated annealing with multiple-search paths and parallel computation for a comprehensive flowshop scheduling problem [J].
Defersha, Fantahun M. .
INTERNATIONAL TRANSACTIONS IN OPERATIONAL RESEARCH, 2015, 22 (04) :669-691
[10]   An improved branch-and-bound algorithm for the two machine total completion time flow shop problem [J].
Della Croce, F ;
Ghirardi, M ;
Tadei, R .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2002, 139 (02) :293-301