Design and operation of dynamic assembly lines using work-sharing

被引:29
作者
Anuar, Rouie [1 ]
Bukchin, Yossi [1 ]
机构
[1] Tel Aviv Univ, Fac Engn, Dept Ind Engn, IL-69978 Tel Aviv, Israel
关键词
work-sharing; assembly lines; dynamic line balancing; cross training;
D O I
10.1080/00207540600707372
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Dynamic line balancing (DLB) deals with dynamic shifting of assembly tasks ( shared tasks) between consecutive stations during the operation of the assembly line. In traditional assembly lines, work-sharing is not allowed. Consequently, the cycle time is determined by the amount of work performed in the most loaded station. The DLB approach enables achieving a shorter cycle time and a higher throughput rate, as compared to the traditional lines. In the implementation of the DLB approach the following has to be determined: ( 1) the identity of the shared tasks, and ( 2) the operational task allocation rule. In some cases, the data regarding the percentage of cycles each shared task will be performed in a station is also required. We first analyse a case in which an initial task assignment to stations ( line balance solution) and the identity of the shared tasks is known and given. Conditions for the balanceability ( the ability of the DLB to achieve an equivalent performance to a perfect balanced line in the steady state) are developed, as well as the formulation for minimizing the cycle time. Next, the sharing costs are considered and approaches for minimizing the shared time and sharing cost are presented, based on the new concept of bottleneck segment. The operational aspect is also addressed, while examining the effect of several state-dependent and state-independent operating rules for task allocation on the cycle time and the system work in process.
引用
收藏
页码:4043 / 4065
页数:23
相关论文
共 14 条
[1]   A production line that balances itself [J].
Bartholdi, JJ ;
Eisenstein, DD .
OPERATIONS RESEARCH, 1996, 44 (01) :21-34
[2]   A SURVEY OF EXACT ALGORITHMS FOR THE SIMPLE ASSEMBLY LINE BALANCING PROBLEM [J].
BAYBARS, I .
MANAGEMENT SCIENCE, 1986, 32 (08) :909-932
[3]  
Bischak DP, 1996, IIE TRANS, V28, P723
[4]   A COMPREHENSIVE LITERATURE-REVIEW AND ANALYSIS OF THE DESIGN, BALANCING AND SCHEDULING OF ASSEMBLY SYSTEMS [J].
GHOSH, S ;
GAGNON, RJ .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1989, 27 (04) :637-670
[5]   Agile workforce evaluation: a framework for cross-training and coordination [J].
Hopp, WJ ;
Van Oyen, MP .
IIE TRANSACTIONS, 2004, 36 (10) :919-940
[6]   Benefits of skill chaining in serial production lines with cross-trained workers [J].
Hopp, WJ ;
Tekin, E ;
Van Oyen, MP .
MANAGEMENT SCIENCE, 2004, 50 (01) :83-98
[7]  
McClain J. O., 2000, Manufacturing & Service Operations Management, V2, P49, DOI 10.1287/msom.2.1.49.23263
[8]   ON-THE-FLY LINE BALANCING WITH VERY LITTLE WIP [J].
MCCLAIN, JO ;
THOMAS, LJ ;
SOX, C .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 1992, 27 (03) :283-289
[9]  
Monden Y., 1983, TOYOTA PRODUCTION SY
[10]  
Ostolaza J., 1990, Journal of Manufacturing and Operations Management, V3, P105