An application of WASPAS method in risk qualitative analysis: a case study of a road construction project in Iran

被引:41
作者
Badalpur, Mohammadreza [1 ]
Nurbakhsh, Ehsan [2 ]
机构
[1] Azad Univ, Tehran South Branch, Tehran, Iran
[2] Azad Univ, Tehran North Branch, Tehran, Iran
关键词
Risk assessment; risk qualitative analysis; road construction project; WASPAS method; FUZZY AHP; MANAGEMENT; SELECTION; PRICE; MODEL;
D O I
10.1080/15623599.2019.1595354
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Today, the focus on risks and uncertain events is one of the essential goals of any organization. If hazards are not taken into consideration at the planning stage it could be dangerous during project life cycle. Therefore, risk assessment is so important which has been extensively investigated by many researchers in recent years. This research suggested a method based on a combination of two WSM models (weighted sum model) and WPM (weighted product model), known as the weighted aggregated sum product assessment (WASPAS) method which was employed to assess negative effects of risks on project. This method has capability and more accuracy compared to independent methods in alternatives ranking. The WASPAS method is one of the new multi-index decision-making techniques which has been adopted and employed in many areas. In this research, we identified and evaluated the risks of a road construction project in Iran which the results showed inaccessibility/inappropriate of barrow pits, loss of key manpower during project life cycle, employing inexperienced subcontractors are of the most important risks among identified risks. Also this paper suggested the WASPAS method as a suitable method with more accuracy among MCDM techniques for evaluating of risks in a real situation.
引用
收藏
页码:910 / 918
页数:9
相关论文
共 35 条
[21]   Regression modelling of risk impacts on construction cost flow forecast [J].
Odeyinka, Henry ;
Lowe, John ;
Kaka, Ammar .
JOURNAL OF FINANCIAL MANAGEMENT OF PROPERTY AND CONSTRUCTION, 2012, 17 (03) :203-+
[22]   Risk analysis in fixed-price design-build construction projects [J].
Öztas, A ;
Ökmen, Ö .
BUILDING AND ENVIRONMENT, 2004, 39 (02) :229-237
[23]   RISK MANAGEMENT IN ROAD CONSTRUCTION: THE CASE OF SRI LANKA [J].
Perera, B. A. K. S. ;
Dhanasinghe, Indika ;
Rameezdeen, Raufdeen .
INTERNATIONAL JOURNAL OF STRATEGIC PROPERTY MANAGEMENT, 2009, 13 (02) :87-102
[24]   SELECTION OF FACADE'S ALTERNATIVES OF COMMERCIAL AND PUBLIC BUILDINGS BASED ON MULTIPLE CRITERIA [J].
Saparauskas, Jonas ;
Zavadskas, Edmundas Kazimieras ;
Turskis, Zenonas .
INTERNATIONAL JOURNAL OF STRATEGIC PROPERTY MANAGEMENT, 2011, 15 (02) :189-203
[25]  
Seyedhoseini SM, 2009, SCI IRAN TRANS E, V16, P138
[26]  
SHANNON CE, 1948, BELL SYST TECH J, V27, P379, DOI DOI 10.1002/J.1538-7305.1948.TB01338.X
[27]  
Sharaf M.M. M., 2015, J. Civ. Eng. Archit, V9, DOI DOI 10.17265/1934-7359/2015.05.004
[28]   Delivery risk analysis within the context of program management using fuzzy logic and DEA: A China case study [J].
Shi, Qian ;
Zhou, Yikun ;
Xiao, Chao ;
Chen, Rongyi ;
Zuo, Jian .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2014, 32 (02) :341-349
[29]   Risk management workshop application: a case study of Ahwaz Urban Railway project [J].
Tavakolan, Mehdi ;
Mohammadi, Amir .
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2018, 18 (03) :260-274
[30]   Construction projects selection and risk assessment by fuzzy AHP and fuzzy TOPSIS methodologies [J].
Taylan, Osman ;
Bafail, Abdallah O. ;
Abdulaal, Reda M. S. ;
Kabli, Mohammed R. .
APPLIED SOFT COMPUTING, 2014, 17 :105-116