Organizing Wendelstein 7-X device operation

被引:1
作者
van Eeten, P. [1 ]
Bosch, H. S. [1 ]
Brakel, R. [1 ]
Degenkolbe, S. [1 ]
机构
[1] Max Planck Inst Plasma Phys, Wendelsteinstr 1, D-17491 Greifswald, Germany
关键词
Wendelstein; 7-X; Commissioning; Operation; Organisation; Responsibilities; STELLARATOR; SYSTEM; SAFETY;
D O I
10.1016/j.fusengdes.2020.111843
中图分类号
TL [原子能技术]; O571 [原子核物理学];
学科分类号
0827 ; 082701 ;
摘要
The super conducing stellarator Wendelstein 7-X (Bosch a al., 2017) started its first operational phase in October 2015 at the Max-Planck-Institute for Plasma Physics in Greifswald with the goal to verify that a stellarator magnetic confinement concept is a viable option for a fusion power plant, i.e. showing confinement comparable to tokamaks and running in steady state operation. Between 2015 and 2018 the first three experimental campaigns (operational phases) OP1.1, OP1.2a and OP1.2b of the W7-X stellarator have been successfully completed. Roughly 13 Months of operational time have been accumulated and have already shown the impressive capability and reliability of W7-X in achieving the physical and technical goals as set by the project. The working group Device Operation (DO) has implemented an organizational structure and workflow to ensure safe and reliable operation of the W7-X device. DO is responsible for planning and executing the commissioning and operation of the W7-X device. The operations plan is based on the physics planning which is a selection of individual physics proposals keeping in mind the technical limitations of W7-X. The operations plan is iterated between the lead physicists and device operation team (DOT). The "technischer Leiter vom Dienst" (TLvD or Engineer in Charge) plays a central role within the DOT in coordinating and supervising the technical operation of W7-X. To ensure safe and reliable operation of W7-X several procedures have been implemented and improved. This involves commissioning templates, checklists, procedures for e.g. plasma heating energy release, operation malfunction cards, logbooks, coordination meetings, duty-on-call and shift-planning. This paper will summarize the organizational aspects of W7-X technical operation as performed in the first three phases. It will also provide an outlook on the upcoming OP2 (actively cooled divertor) with the requirements for technical operation regarding commissioning and operation towards steady state plasma operation.
引用
收藏
页数:6
相关论文
共 50 条
  • [21] Cryotechnology for Wendelstein 7-X
    Schauer, F
    Bau, H
    Bozhko, Y
    Brockmann, R
    Nagel, M
    Pietsch, M
    Raatz, S
    FUSION ENGINEERING AND DESIGN, 2003, 66-68 : 1045 - 1048
  • [22] Cyclic Behavior of Wendelstein 7-X Magnet System During First Two Phases of Operation
    Bykov, Victor
    Zhu, Jiawu
    Carls, Andre
    Hein, Bernd
    Risse, Konrad
    van Eeten, Paul
    Bosch, Hans-Stephan
    Wegener, Lutz
    IEEE TRANSACTIONS ON APPLIED SUPERCONDUCTIVITY, 2020, 30 (04)
  • [23] Error fields in the Wendelstein 7-X stellarator
    Lazerson, Samuel A.
    Bozhenkov, Sergey
    Israeli, Ben
    Otte, Matthias
    Niemann, Holger
    Bykov, Victor
    Endler, Michael
    Andreeva, Tamara
    Ali, Adnan
    Drewelow, Peter
    Jakubowski, Marcin
    Sitjes, Aleix Puig
    Pisano, Fabio
    Cannas, Barbara
    PLASMA PHYSICS AND CONTROLLED FUSION, 2018, 60 (12)
  • [24] Progress and Challenges in the Construction of Wendelstein 7-X
    Braeuer, Torsten
    Klinger, Thomas
    Bosch, Hans-Stephan
    2011 IEEE/NPSS 24TH SYMPOSIUM ON FUSION ENGINEERING (SOFE), 2011,
  • [25] On the accuracy of port assembly at Wendelstein 7-X
    Braeuer, Torsten
    FUSION ENGINEERING AND DESIGN, 2013, 88 (6-8) : 721 - 724
  • [26] Tuning of the rotational transform in Wendelstein 7-X
    Lazerson, Samuel A.
    Gao, Yu
    Hammond, Kenneth
    Killer, Carsten
    Schlisio, Georg
    Otte, Matthias
    Biedermann, Christoph
    Spolaore, Monica
    Bozhenkov, Sergey
    Geiger, Joachim
    Grulke, Olaf
    Nicolai, Dirk
    Satheeswaran, Guruparan
    Niemann, Holger
    Jakubowski, Marcin
    Drewelow, Peter
    Sitjes, Aleix Puig
    Ali, Adnan
    Cannas, Barbara
    Pisano, Fabio
    Koenig, Ralph
    Wurden, Glen
    Kocsis, Gabor
    Szepesi, Tamas
    Wenzel, Uwe
    Mulsow, Matthias
    Rahbarnia, Kian
    Schilling, Jonathan
    Neuner, Ulrich
    Andreeva, Tamara
    Thomsen, Henning
    Knauer, Jens
    Brunner, Kai Jakob
    Blackwell, Boyd
    Endler, Michael
    Klose, Soren
    Rudischhauser, Lukas
    NUCLEAR FUSION, 2019, 59 (12)
  • [27] The Set of Diagnostics for the First Operation Campaign of the Wendelstein 7-X Stellarator
    Koenig, Ralf
    Baldzuhn, J.
    Biel, W.
    Biedermann, C.
    Bosch, H. S.
    Bozhenkov, S.
    Braeuer, T.
    Brotas de Carvalho, B.
    Burhenn, R.
    Buttenschoen, B.
    Cseh, G.
    Czarnecka, A.
    Endler, M.
    Erckmann, V.
    Estrada, T.
    Geiger, J.
    Grulke, O.
    Hartmann, D.
    Hathiramani, D.
    Hirsch, M.
    Onski, S. Jabl
    Jakubowski, M.
    Kaczmarczyk, J.
    Klinger, T.
    Klose, S.
    Kocsis, G.
    Kornejew, P.
    Kraemer-Flecken, A.
    Kremeyer, T.
    Krychowiak, M.
    Kubkowska, M.
    Langenberg, A.
    Laqua, H. P.
    Laux, M.
    Liang, Y.
    Lorenz, A.
    Marchuk, A. O.
    Moncada, V.
    Neubauer, O.
    Neuner, U.
    Oosterbeek, J. W.
    Otte, M.
    Pablant, N.
    Pasch, E.
    Pedersen, T. S.
    Rahbarnia, K.
    Ryc, L.
    Schmitz, O.
    Schneider, W.
    Schuhmacher, H.
    JOURNAL OF INSTRUMENTATION, 2015, 10
  • [28] Runtime resource checking at WENDELSTEIN 7-X during plasma operation
    Laqua, Heike
    Schacht, Joerg
    Spring, Anett
    FUSION ENGINEERING AND DESIGN, 2007, 82 (5-14) : 982 - 987
  • [29] Design and construction of WENDELSTEIN 7-X
    Wanner, M
    Feist, JH
    Renner, H
    Sapper, J
    Schauer, F
    Schneider, H
    Erckmann, V
    Niedermeyer, H
    FUSION ENGINEERING AND DESIGN, 2001, 56-57 : 155 - 162
  • [30] Project control of WENDELSTEIN 7-X
    Bünde, R
    Gottschewsky, M
    Heinrich, S
    FUSION ENGINEERING AND DESIGN, 2001, 58-59 : 803 - 808