Commissioning Integrated Process at Industrial Plants

被引:1
|
作者
Alves Ney, Gloria Maria [1 ]
Fortes, Marcio Zamboti [1 ]
机构
[1] Fluminense Fed Univ, Engn Sch, MPMI, Passo Patria St 156,E-431 Room, BR-24210240 Niteroi, RJ, Brazil
关键词
Commissioning; Gasification Process; Flowchart; ARENA Software; GASIFICATION;
D O I
10.12700/APH.16.7.2019.7.8
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper is a case study about the gasification system commissioning. After collecting data and information about this system analysis were made, related to TEXACO, SHELL, LURGI and E-GAS, then a flowchart was created. Simulations were made in the ARENA software for verification of commissioning performance. The results showed the importance of commissioning management in a standard commissioning process and other integrated proposed were compared.
引用
收藏
页码:133 / 148
页数:16
相关论文
共 50 条
  • [21] From use cases of the Joint European Torus towards integrated commissioning requirements of the ITER tokamak
    Neto, A. C.
    Stephen, A.
    Sartori, F.
    Cavinato, M.
    Farthing, J. W.
    Ranz, R.
    Saibene, G.
    Winter, A.
    Arnoux, G.
    Alves, D.
    Blackman, T.
    Boboc, A.
    Card, P. J.
    Dalley, S.
    Day, I. E.
    De Tommasi, G.
    Drewelow, P.
    Elsmore, C.
    Ivings, E.
    Felton, R.
    Gerasimov, S.
    Goodyear, A.
    Heesterman, P.
    Hogben, C.
    Hotchin, S.
    Kinna, D.
    Lomas, P. J.
    Mailloux, J.
    McCullen, P.
    Rimini, F. G.
    Shaw, S. R.
    Valcarcel, D. F.
    Waterhouse, J.
    Zastrow, K. -D.
    FUSION ENGINEERING AND DESIGN, 2015, 96-97 : 672 - 675
  • [22] Novel approach for wireless commissioning and assisted process development based on Bluetooth Low Energy
    Christoph, Pallasch
    Alexander, Peitz
    Werner, Herfs
    Anke, Schmeink
    Guido, Dartmann
    2018 IEEE 23RD INTERNATIONAL CONFERENCE ON EMERGING TECHNOLOGIES AND FACTORY AUTOMATION (ETFA), 2018, : 235 - 242
  • [23] The active commissioning process for a power reactor spent fuel reprocessing pilot plant in China
    ZHANG TianXiang *
    Science Bulletin, 2011, (23) : 2411 - 2415
  • [24] The active commissioning process for a power reactor spent fuel reprocessing pilot plant in China
    Zhang TianXiang
    Wang Jian
    Wu Tao
    Chen GuangJun
    Di Wu YongQing
    Ru FaQuan
    CHINESE SCIENCE BULLETIN, 2011, 56 (23): : 2411 - 2415
  • [25] Performance of integrated gasification combined cycle power plants integrated with methanol synthesis processes
    Carapellucci, R
    Cau, G
    Cocco, D
    PROCEEDINGS OF THE INSTITUTION OF MECHANICAL ENGINEERS PART A-JOURNAL OF POWER AND ENERGY, 2001, 215 (A3) : 347 - 356
  • [26] A consensus-based, process commissioning template for high-dose-rate gynecologic treatments
    Browns, Derek W.
    Damato, Antonio L.
    Sutlief, Steven
    Morcovescu, Serban
    Park, Sang-June
    Reiff, Jay
    Shih, Allen
    Scanderbeg, Daniel J.
    BRACHYTHERAPY, 2016, 15 (05) : 570 - 577
  • [27] Process development of sustainable biorefinery system integrated into the existing pulping process
    Mongkhonsiri, Ghochapon
    Charoensuppanimit, Pongtorn
    Anantpinijwatna, Amata
    Gani, Rafiqul
    Assabumrungrat, Suttichai
    JOURNAL OF CLEANER PRODUCTION, 2020, 255
  • [28] Using Co-Commissioning to Deliver Integrated Care: The Hunter New England Diabetes Alliance Model of Care
    Turner, Catherine
    Rebbeck, Jay
    INTERNATIONAL JOURNAL OF INTEGRATED CARE, 2018, 18
  • [29] Evidence-based policy-making in the NHS: exploring the interface between research and the commissioning process
    Harries, U
    Elliott, H
    Higgins, A
    JOURNAL OF PUBLIC HEALTH MEDICINE, 1999, 21 (01): : 29 - 36
  • [30] SIMULATION OF LIQUID-GAS REPLACEMENT IN COMMISSIONING PROCESS FOR LARGE-SLOPE CRUDE OIL PIPELINE
    Chen, Yuanyuan
    Gong, Jing
    Li, Xiaoping
    Zhang, Nan
    He, Shaojun
    Liu, Jianfeng
    Liu, Yuwei
    Wu, Jiawen
    PROCEEDINGS OF THE 9TH INTERNATIONAL PIPELINE CONFERENCE - 2012, VOL 1, 2013, : 175 - +