Modeling of design iterations through simulation

被引:16
作者
Wang, Wei-Chih [1 ]
Liu, Jang-Jeng [1 ]
Liao, Tzong-Shiun [1 ]
机构
[1] Natl Chiao Tung Univ, Dept Civil Engn, Hsinchu 300, Taiwan
关键词
design iteration; design schedule; design process; dependency structure matrix; simulation;
D O I
10.1016/j.autcon.2005.07.010
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Enhancing the scheduling of a design project can markedly reduce its total duration. However, accurately representing the schedule of a design project is complex, largely owing to that design activities generally depend on information about each other. That is, the design process involves many iterations across activities. Iterative dependency makes difficult defining the logical relationships among activities in the network and evaluating the duration of the project. This work applies a dependency structure matrix to identify design dependencies. Causes and various types of design iterations for a building project are presented. Additionally, an innovative simulation-based model is developed to incorporate the design iterations, deliverables and participants for generating a schedule of a design project. The proposed model can not only assess how design iterations affect the duration, but also evaluate the idle durations of the design participants to support the assignment of design tasks. Effectiveness of the model is demonstrated through its application to an example project. (c) 2005 Elsevier B.V. All rights reserved.
引用
收藏
页码:589 / 603
页数:15
相关论文
共 29 条
[11]  
Chun-Hsien Chen, 2003, International Journal of Project Management, V21, P291, DOI 10.1016/S0263-7863(02)00023-6
[12]  
FERD AS, 1999, UNIFORM DRAWING FORM, P78
[13]   FORECASTING DESIGN-RELATED PROBLEMS - CASE-STUDY [J].
GLAVAN, JR ;
TUCKER, RL .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1991, 117 (01) :47-65
[14]  
HAVILAND D, 1994, PROJECT ARCH HDB PRO, V2
[15]   Improving design coordination for building projects. I: Information model [J].
Hegazy, T ;
Zaneldin, E ;
Grierson, D .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2001, 127 (04) :322-329
[16]  
LIAO TS, 2004, THESIS NATL CHIAO TU
[17]   Scheduling of design projects with uncertain number of iterations [J].
Luh, PB ;
Liu, F ;
Moser, B .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 113 (03) :575-592
[18]  
MARTINEZ JC, 1996, THESIS U MICHIGAN AN
[19]  
Moder J.J., 1983, Project Management with CPM, PERT and Precedence Diagramming
[20]  
MOKHTAR A, 2000, ASCE J ARCH ENG, V6, P66