Open-Pit Mine Optimization with Maximum Satisfiability

被引:5
|
作者
Deutsch, Matthew [1 ]
机构
[1] Colorado Sch Mines, Denver, CO 80401 USA
关键词
Mine planning; Optimization; Maximumsatisfiability; Ultimate pit; Mine scheduling; Mining width; FLOW;
D O I
10.1007/s42461-019-0062-x
中图分类号
TF [冶金工业];
学科分类号
0806 ;
摘要
A common casualty of modern open-pit mine optimization is the assurance that the resulting design is actually achievable. Optimized mine plans that consider value and a bare minimum of precedence constraints do not, in general, translate into practical, operational mine designs that can be used in the field. Ultimate pits may come to a sharp point at the bottom. Schedules may require taking small parcels of material from many disparate areas of the pit in a single period, and grade control polygons may be ragged, narrow, and not minable with realistic equipment. In this paper, all of these problems are addressed by encoding these three fundamental open-pit mine optimization problems as maximum satisfiability problems. Maximum satisfiability provides a useful framework for problems that are non-linear and may guarantee the optimality that metaheuristics cannot.
引用
收藏
页码:757 / 764
页数:8
相关论文
共 50 条
  • [1] Open-Pit Mine Optimization with Maximum Satisfiability
    Matthew Deutsch
    Mining, Metallurgy & Exploration, 2019, 36 : 757 - 764
  • [2] OPTIMIZATION OF AN OPEN-PIT MINE TRANSPORT-SYSTEM
    TENIC, A
    KORDIC, Z
    STROJARSTVO, 1981, 23 (06): : 321 - 329
  • [3] Production schedule optimization in open-pit coal mine
    Gu, Xiao-Wei
    Xu, Xiao-Chuan
    Wang, Qing
    Zheng, You-Yi
    Dongbei Daxue Xuebao/Journal of Northeastern University, 2013, 34 (08): : 1184 - 1187
  • [4] Ultimate pit optimization with environmental problem for open-pit coal mine
    Xu, Xiaochuan
    Gu, Xiaowei
    Wang, Qing
    Zhao, Yunqi
    Zhu, Zhenguo
    Wang, Fengdan
    Zhang, Zaolin
    PROCESS SAFETY AND ENVIRONMENTAL PROTECTION, 2023, 173 : 366 - 372
  • [5] The Influence of Rainfall on Landslide Stability of an Open-Pit Mine: The Case of Haizhou Open-Pit Mine
    An Bo
    Zhu Chun
    Liu Kuiming
    Li Sitong
    Tao Zhigang
    Li Haipeng
    Yu Haoran
    GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2019, 37 (04) : 3367 - 3378
  • [6] The Influence of Rainfall on Landslide Stability of an Open-Pit Mine: The Case of Haizhou Open-Pit Mine
    An Bo
    Zhu Chun
    Liu Kuiming
    Li Sitong
    Tao Zhigang
    Li Haipeng
    Yu Haoran
    Geotechnical and Geological Engineering, 2019, 37 : 3367 - 3378
  • [7] Study on Optimization of Coal Truck Flow in Open-Pit Mine
    Bao, Haiming
    Zhang, Ruixin
    ADVANCES IN CIVIL ENGINEERING, 2020, 2020
  • [8] Study on blasting parameters optimization in Anjialing open-pit mine
    Huang Xiaoming
    Zhang Ruixin
    Sun Qiang
    PROGRESS IN MINING SCIENCE AND SAFETY TECHNOLOGY, PTS A AND B, 2007, : 793 - 798
  • [9] Dynamic optimization of open-pit cutoff grade by the maximum principle
    Xie, Yingliang
    Xie, Linhai
    PROCEEDINGS OF THE 2007 CONFERENCE ON SYSTEMS SCIENCE, MANAGEMENT SCIENCE AND SYSTEM DYNAMICS: SUSTAINABLE DEVELOPMENT AND COMPLEX SYSTEMS, VOLS 1-10, 2007, : 2435 - 2441
  • [10] ECSTALL STORY - OPEN-PIT MINE
    COUPLAND, GC
    CIM BULLETIN, 1974, 67 (745): : 64 - 69