Stability Analysis of TBM Tunnel Undercrossing Existing High-Speed Railway Tunnel: A Case Study from Yangtaishan Tunnel of Shenzhen Metro Line 6

被引:9
|
作者
Zhao, Mingji [1 ]
Cheng, Yun [2 ,3 ]
Song, Zhanping [2 ,3 ]
Wang, Tong [2 ,3 ]
Zhang, Yuwei [2 ,3 ]
Gong, Yitong [2 ]
Song, Yuncai [4 ]
机构
[1] Xian Univ Architecture & Technol, Sch Mech & Elect Engn, Xian 710055, Peoples R China
[2] Xian Univ Architecture & Technol, Sch Civil Engn, Xian 710055, Peoples R China
[3] Shaanxi Key Lab Geotech & Underground Space Engn, Xian 710055, Peoples R China
[4] China Railway Construct Bridge Engn Bur Grp Co Lt, Tianjin 300300, Peoples R China
关键词
D O I
10.1155/2021/6674862
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
During the construction of the underpass of a new tunnel, the excavation unloading effect disturbs surrounding rock masses and promotes surrounding rock deformation, inevitably changing stress and displacement in the existing tunnel. Taking Yangtaishan tunnel excavation of Shenzhen Metro Line 6 as an engineering example, effects of excavation programs of left and right lines on the deformation characteristics of newly excavated and existing tunnels were evaluated based on Midas numerical model and priority excavation advantages of the left line were determined. The settlement and horizontal deformation characteristics of the existing tunnel were analyzed using the construction monitoring method. Results showed that maximum settlement and horizontal deformation of the existing tunnel were 1.35 and 0.23 mm, respectively. Settlement of invert and inverted top along axis direction was from growth to decline, and then a V-shaped settlement trough was formed with maximum settlement values of 1.36 and 0.97 mm, respectively. Maximum settlement and uplift of the newly built tunnel appeared on the upper and bottom parts of invert, respectively. In the newly built tunnel segments, the top settlement was dominated and deformation was mainly distributed in both side areas. At the top of the existing tunnel segment, convergence settlement was 3.09 mm and settlement rate was slow first which was accelerated, then stabilized, and finally slowed down again which was opposite to the uplift development trend of the bottom of tunnel segment. The top of the existing tunnel segment showed four settlement stages, slow, rapid, stable, and slow settlement stages. Compared with the right line, preferential excavation of the left line had obvious advantages in terms of tunnel stability. The unloading effect of TBM excavation created vault settlement in the existing tunnels where actual settlement values were 1.12 and 1.13 times, which theoretically calculated settlement. The horizontal deformation of the existing tunnel was varied first linearly and then nonlinearly with maximum deformation in the convergence stage of 1.47 mm.
引用
收藏
页数:18
相关论文
共 50 条
  • [1] Experimental and Numerical Studies of a Shield Twin Tunnel Undercrossing the Existing High-Speed Railway Tunnel
    Ruizhen Fei
    Limin Peng
    Chunlei Zhang
    Jiqing Zhang
    Peng Zhang
    Geotechnical and Geological Engineering, 2024, 42 : 1871 - 1886
  • [2] Experimental and Numerical Studies of a Shield Twin Tunnel Undercrossing the Existing High-Speed Railway Tunnel
    Fei, Ruizhen
    Peng, Limin
    Zhang, Chunlei
    Zhang, Jiqing
    Zhang, Peng
    GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2024, 42 (03) : 1871 - 1886
  • [3] Field Test Optimization of Shield Tunnelling Parameters Undercrossing an Existing High-Speed Railway Tunnel: A Case Study
    Huang, Zhen
    Zhang, Hai
    Long, Zhen
    Qiu, Wenge
    Meng, Guowang
    Zhu, Lianchen
    GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2021, 39 (02) : 1381 - 1398
  • [4] Field Test Optimization of Shield Tunnelling Parameters Undercrossing an Existing High-Speed Railway Tunnel: A Case Study
    Zhen Huang
    Hai Zhang
    Zhen Long
    Wenge Qiu
    Guowang Meng
    Lianchen Zhu
    Geotechnical and Geological Engineering, 2021, 39 : 1381 - 1398
  • [5] Analysis on the Influence of Cross Tunnel Construction on the Deformation of the Existing High-Speed Railway Tunnel
    Pan W.
    Gao Z.
    Zheng C.
    Gong Z.
    Geotechnical and Geological Engineering, 2018, 36 (6) : 4001 - 4013
  • [6] Impact Analysis on Existing High-speed Railway Tunnel by the Construction of New Tunnel-Overpass
    Pan Wei-dong
    Chen Jian-gang
    Ou Wen-jun
    ELECTRONIC JOURNAL OF GEOTECHNICAL ENGINEERING, 2016, 21 (17): : 5627 - 5639
  • [8] Mechanical characteristics of twin tunnel underneath construction on existing high-speed railway tunnel
    Fei, Ruizhen
    Peng, Limin
    Zhang, Chunlei
    Zhang, Jiqing
    Zhang, Peng
    ARCHIVES OF CIVIL ENGINEERING, 2023, 69 (01) : 403 - 420
  • [9] Research on the Key Technologies of Construction of TBM Interval Tunnel across High-speed Railway Tunnel
    Zhang, Mingshu
    Gong, Lun
    Chen, Haiyong
    Sun, Xuefei
    Yu, Jingwen
    Journal of Railway Engineering Society, 2019, 36 (07): : 76 - 80
  • [10] Prediction and Control of Existing High-Speed Railway Tunnel Deformation Induced by Shield Undercrossing Based on BO-XGboost
    Fei, Ruizhen
    Wu, Hongtao
    Peng, Limin
    SUSTAINABILITY, 2024, 16 (23)