Discrete time model and algorithms for container yard crane scheduling

被引:100
|
作者
Li, Wenkai [1 ]
Wu, Yong [1 ]
Petering, M. E. H. [1 ,2 ]
Goh, Mark [1 ]
de Souza, Robert [1 ]
机构
[1] Asia Pacific, Logist Inst, Singapore 117574, Singapore
[2] Univ Wisconsin, Dept Ind & Mfg Engn, Milwaukee, WI 53201 USA
关键词
Scheduling; Rolling-horizon algorithm; Container yard; MILP; OPERATIONS-RESEARCH; ALLOCATION; SEARCH;
D O I
10.1016/j.ejor.2008.08.019
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Container terminal (CT) operations are often bottlenecked by slow YC (yard crane) movements. PM (prime mover) queues in front of the YCs are common. Hence, efficient YC scheduling to reduce the PM waiting time is critical in increasing a CT's throughput. We develop an efficient model for YC scheduling by taking into account realistic operational constraints such as inter-crane interference, fixed YC separation distances and simultaneous container storage/retrievals. Among them, only inter-crane interference has ever been considered in the literature. The model requires far fewer integer variables than the literature by using bi-index decision variables. We show how the model can be solved quickly using heuristics and rolling-horizon algorithm, yielding close to optimal solutions in seconds. The solution quality and solution time are both better than the literature even with additional constraints considered. The proposed formulations and algorithms can be extended to other problems with time windows and space constraints. (C) 2008 Elsevier B.V. All rights reserved.
引用
收藏
页码:165 / 172
页数:8
相关论文
共 50 条
  • [31] Integrated internal truck, yard crane and quay crane scheduling in a container terminal considering energy consumption
    He, Junliang
    Huan, Youfang
    Yan, Wei
    Wang, Shuaian
    EXPERT SYSTEMS WITH APPLICATIONS, 2015, 42 (05) : 2464 - 2487
  • [32] A Quay Crane Scheduling Model in Container Terminals
    Tang, Qi
    ADVANCES IN SWARM INTELLIGENCE, PT 2, PROCEEDINGS, 2010, 6146 : 283 - 290
  • [33] A continuous time model for multiple yard crane scheduling with last minute job arrivals
    Li, Wenkai
    Goh, Mark
    Wu, Yong
    Petering, M. E. H.
    de Souza, R.
    Wu, Y. C.
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2012, 136 (02) : 332 - 343
  • [34] Optimization of Gantry Crane Scheduling in Container Sea-Rail Intermodal Transport Yard
    Luo, Tian
    Chang, Daofang
    Gao, Yinping
    MATHEMATICAL PROBLEMS IN ENGINEERING, 2018, 2018
  • [35] A new solution approach for the twin yard crane scheduling problem in automated container terminals
    Oladugba, Andrew Omoniyi
    Gheith, Mohamed
    Eltawil, Amr
    ADVANCED ENGINEERING INFORMATICS, 2023, 57
  • [36] A comprehensive review of quay crane scheduling, yard operations and integrations thereof in container terminals
    Kizilay, Damla
    Eliiyi, Deniz Tursel
    FLEXIBLE SERVICES AND MANUFACTURING JOURNAL, 2021, 33 (01) : 1 - 42
  • [37] A comprehensive review of quay crane scheduling, yard operations and integrations thereof in container terminals
    Damla Kizilay
    Deniz Türsel Eliiyi
    Flexible Services and Manufacturing Journal, 2021, 33 : 1 - 42
  • [38] Integrated Scheduling of Dual-cycle AGV and Yard Crane at Automated Container Terminal
    Tian Y.
    Zhou Q.
    Zhu B.-F.
    Jiaotong Yunshu Xitong Gongcheng Yu Xinxi/Journal of Transportation Systems Engineering and Information Technology, 2020, 20 (04): : 216 - 223and243
  • [39] Optimization Approach for Yard Crane Scheduling Problem under a combined constraints in Container Terminals
    Torbi, Imane
    Aidi, Sanaa
    Mazouzi, Mohamed
    Belassiria, Imad
    2022 14TH INTERNATIONAL COLLOQUIUM OF LOGISTICS AND SUPPLY CHAIN MANAGEMENT (LOGISTIQUA2022), 2022, : 412 - 417
  • [40] Two Yard Crane Scheduling With Dynamic Processing Time and Interference
    Zheng, Feifeng
    Man, Xiaoyi
    Chu, Feng
    Liu, Ming
    Chu, Chengbin
    IEEE TRANSACTIONS ON INTELLIGENT TRANSPORTATION SYSTEMS, 2018, 19 (12) : 3775 - 3784