Optimization model for long-distance integrated transmission of wind farms and pumped-storage hydropower plants

被引:76
作者
Su, Chengguo [1 ]
Cheng, Chuntian [1 ]
Wang, Peilin [2 ]
Shen, Jianjian [1 ]
Wu, Xinyu [1 ]
机构
[1] Dalian Univ Technol, Inst Hydropower & Hydroinformat, Dalian 116024, Peoples R China
[2] Yellow River Conservancy Tech Inst, Sch Hydraul Engn, Kaifeng 475004, Peoples R China
基金
中国国家自然科学基金;
关键词
Integrated transmission; Wind farm; Pumped-storage hydropower plant; Wind power forecast errors; Mixed-integer linear programming; POWER; ENERGY; GENERATION; OPERATION; TECHNOLOGIES;
D O I
10.1016/j.apenergy.2019.03.080
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
Long-distance and large-capacity wind power transmission from western and northern China to load centers through ultra-high voltage (UHV) transmission lines is an important and effective measure for large-scale wind power accommodation in China. This paper proposes a novel practical integrated transmission mode for a wind farm (WF) and a pumped-storage hydropower plant (PSHP). In order to cope with additional imbalance costs caused by deviations from the submitted day-ahead schedule and increase the total operational profit, an optimization model for the integrated transmission of a WF and a PSHP has been formulated. The forecast errors for wind power generation are modeled by a scenario analysis technique. Hydraulic constraints and the head effect on the performance of each pumped-storage hydropower unit (PSHU) in both generating and pumping modes have been considered. Through incorporating the nonlinearities, including constraints on the operation status of units and turbine performance curves, the model is converted into a mixed-integer linear programming (MILP) formulation using piecewise linear approximation techniques. Case studies demonstrate that the integrated transmission of the WF and PHSP can efficiently alleviate the negative effect of wind power fluctuations and significantly increase profit. Sensitivity analyses have been carried out to evaluate the effect of the penalty factor for energy imbalance and the electricity price mechanism in the receiving-end power grid on the overall performance of the WF-PSHP union.
引用
收藏
页码:285 / 293
页数:9
相关论文
共 34 条
[1]   Energy storage technologies and real life applications - A state of the art review [J].
Aneke, Mathew ;
Wang, Meihong .
APPLIED ENERGY, 2016, 179 :350-377
[2]  
Argyrou MC, 2018, RENEW SUST ENERG REV, V179, P350
[3]   Pumped hydro storage plants with improved operational flexibility using constant speed Francis runners [J].
Beevers, D. ;
Branchini, L. ;
Orlandini, V. ;
De Pascale, A. ;
Perez-Blanco, H. .
APPLIED ENERGY, 2015, 137 :629-637
[4]   An MILP approach for short-term hydro scheduling and unit commitment with head-dependent reservoir [J].
Borghetti, Alberto ;
D'Ambrosio, Claudia ;
Lodi, Andrea ;
Martello, Silvano .
IEEE TRANSACTIONS ON POWER SYSTEMS, 2008, 23 (03) :1115-1124
[5]   Wind powered pumped hydro storage systems, a means of increasing the penetration of renewable energy in the Canary Islands [J].
Bueno, C. ;
Carta, J. A. .
RENEWABLE & SUSTAINABLE ENERGY REVIEWS, 2006, 10 (04) :312-340
[6]   On the optimization of the daily operation of a wind-hydro power plant [J].
Castronuovo, ED ;
Lopes, JAP .
IEEE TRANSACTIONS ON POWER SYSTEMS, 2004, 19 (03) :1599-1606
[7]   Optimal operation and hydro storage sizing of a wind-hydro power plant [J].
Castronuovo, ED ;
Lopes, JAP .
INTERNATIONAL JOURNAL OF ELECTRICAL POWER & ENERGY SYSTEMS, 2004, 26 (10) :771-778
[8]   Integrated Energy Systems for Higher Wind Penetration in China: Formulation, Implementation, and Impacts [J].
Chen, Xinyu ;
McElroy, Michael B. ;
Kang, Chongqing .
IEEE TRANSACTIONS ON POWER SYSTEMS, 2018, 33 (02) :1309-1319
[9]   Hydro Unit Commitment With a Head-Sensitive Reservoir and Multiple Vibration Zones Using MILP [J].
Cheng, Chuntian ;
Wang, Jiayang ;
Wu, Xinyu .
IEEE TRANSACTIONS ON POWER SYSTEMS, 2016, 31 (06) :4842-4852
[10]  
China Electricity Council, 2016, EL IND DEV STAT CHIN