A hybrid method for large-scale short-term scheduling of make-and-pack production processes

被引:28
|
作者
Baumann, Philipp [1 ]
Trautmann, Norbert [1 ]
机构
[1] Univ Bern, Dept Business Adm, CH-3012 Bern, Switzerland
基金
瑞士国家科学基金会;
关键词
Scheduling; Make-and-pack production; Hybrid method; Real-world production process; MULTISTAGE BATCH PLANTS; CONTINUOUS-TIME REPRESENTATION; MIXED-INTEGER; GENETIC ALGORITHM; SINGLE-STAGE; MILP MODEL; FORMULATION; FRAMEWORK; FLOWSHOP;
D O I
10.1016/j.ejor.2013.12.040
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Due to the ongoing trend towards increased product variety, fast-moving consumer goods such as food and beverages, pharmaceuticals, and chemicals are typically manufactured through so-called make-and-pack processes. These processes consist of a make stage, a pack stage, and intermediate storage facilities that decouple these two stages. In operations scheduling, complex technological constraints must be considered, e.g., non-identical parallel processing units, sequence-dependent changeovers, batch splitting, no-wait restrictions, material transfer times, minimum storage times, and finite storage capacity. The short-term scheduling problem is to compute a production schedule such that a given demand for products is fulfilled, all technological constraints are met, and the production makespan is minimised. A production schedule typically comprises 500-1500 operations. Due to the problem size and complexity of the technological constraints, the performance of known mixed-integer linear programming (MILP) formulations and heuristic approaches is often insufficient. We present a hybrid method consisting of three phases. First, the set of operations is divided into several subsets. Second, these subsets are iteratively scheduled using a generic and flexible MILP formulation. Third, a novel critical path-based improvement procedure is applied to the resulting schedule. We develop several strategies for the integration of the MILP model into this heuristic framework. Using these strategies, high-quality feasible solutions to large-scale instances can be obtained within reasonable CPU times using standard optimisation software. We have applied the proposed hybrid method to a set of industrial problem instances and found that the method outperforms state-of-the-art methods. (C) 2014 Elsevier B.V. All rights reserved.
引用
收藏
页码:718 / 735
页数:18
相关论文
共 50 条
  • [41] Short-term scheduling and recipe optimization of blending processes
    Glismann, K
    Gruhn, G
    COMPUTERS & CHEMICAL ENGINEERING, 2001, 25 (4-6) : 627 - 634
  • [42] Short-term dynamics of sea scallops and their predators following large-scale seeding
    Nadeau, Madeleine
    Brethes, Jean-Claude
    Barbeau, Myriam A.
    JOURNAL OF SHELLFISH RESEARCH, 2007, 26 (04): : 1328 - 1329
  • [43] Using Short-Term Monitoring Data to Achieve Goals in a Large-Scale Restoration
    Hagen, Dagmar
    Evju, Marianne
    ECOLOGY AND SOCIETY, 2013, 18 (03):
  • [44] Data Processing Pipeline of Short-Term Depression Detection with Large-Scale Dataset
    Lee, Yonggeon
    Noh, Youngtae
    Lee, Uichin
    2023 IEEE INTERNATIONAL CONFERENCE ON BIG DATA AND SMART COMPUTING, BIGCOMP, 2023, : 391 - 392
  • [45] Hybrid Model for Short-Term Scheduling of Hydropower Systems
    Hidalgo, Ieda G.
    Correia, Paulo B.
    Arnold, Francisco J.
    Estrocio, Joao Paulo F.
    de Barros, Regiane S.
    Fernandes, Jessica P. T.
    Yeh, William W. -G.
    JOURNAL OF WATER RESOURCES PLANNING AND MANAGEMENT, 2015, 141 (03)
  • [46] A hybrid approach to large-scale job shop scheduling
    Rui Zhang
    Cheng Wu
    Applied Intelligence, 2010, 32 : 47 - 59
  • [47] A hybrid approach to large-scale job shop scheduling
    Zhang, Rui
    Wu, Cheng
    APPLIED INTELLIGENCE, 2010, 32 (01) : 47 - 59
  • [48] Production Scheduling of a Large-Scale Steelmaking Continuous Casting Process via Unit-Specific Event-Based Continuous-Time Models: Short-Term and Medium-Term Scheduling
    Li, Jie
    Xiao, Xin
    Tang, Qiuhua
    Floudas, Christodoulos A.
    INDUSTRIAL & ENGINEERING CHEMISTRY RESEARCH, 2012, 51 (21) : 7300 - 7319
  • [49] SHORT-TERM PRODUCTION SCHEDULING OF THE PULP-MILL
    LEIVISKA, K
    ACTA POLYTECHNICA SCANDINAVICA-MATHEMATICS AND COMPUTER SCIENCE SERIES, 1982, (36): : 1 - 180
  • [50] SHORT-TERM PRODUCTION SCHEDULING OF AN AUTOMATED MANUFACTURING FACILITY
    GERSHWIN, SB
    AKELLA, R
    CHOONG, YF
    IBM JOURNAL OF RESEARCH AND DEVELOPMENT, 1985, 29 (04) : 392 - 400