A linear time-cost tradeoff problem with multiple milestones under a comb graph

被引:5
作者
Choi, Byung-Cheon [1 ]
Kang, Changmuk [2 ]
机构
[1] Chungnam Natl Univ, Dept Business Adm, 79 Daehangno, Daejeon 305704, South Korea
[2] Soongsil Univ, Dept Ind & Informat Syst Engn, 369 Sangdo Ro, Seoul 156743, South Korea
基金
新加坡国家研究基金会;
关键词
Project scheduling; Time-cost tradeoff; Multiple milestones; Comb graph; COMPLEXITY; ALGORITHMS;
D O I
10.1007/s10878-019-00385-2
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
We consider a linear time-cost tradeoff problem (LTCTP) with multiple milestones under a comb graph. A time-cost tradeoff problem decides whether and how much to spend a cost to compress processing time of a job in order to meet promised due dates. This is common in managing a project because additional labors or resources are expensive. It is called linear where the compression cost linearly increases with reduced time. An objective of the LTCTP that this study addresses is to minimize the weighted number of tardy milestones plus the total compression cost. This study considers a special precedence structure, which is called a comb graph. A chain of jobs that sequentially precede each other forms a main process of a project, and other chains of jobs, corresponding to sub processes, precede each job in the main process. For this structure, we developed a strongly-polynomial-time algorithm. This is the first result of unveiling complexity of the multi-milestone LTCTP under a non-chain structure.
引用
收藏
页码:341 / 361
页数:21
相关论文
共 18 条
[1]   FASTER ALGORITHMS FOR THE SHORTEST-PATH PROBLEM [J].
AHUJA, RK ;
MEHLHORN, K ;
ORLIN, JB ;
TARJAN, RE .
JOURNAL OF THE ACM, 1990, 37 (02) :213-223
[2]  
Artigues C., 2008, Resource-constrained project scheduling: models, algorithms, extensions and applications
[3]  
Bruker P., 1999, EUR J OPER RES, V112, P3
[4]  
Byung-Cheon Choi, 2016, Management Science & Financial Engineering, V22, P5, DOI 10.7737/MSFE.2016.22.1.005
[5]  
Choi B-C, 2013, KOREAN OPERATIONS RE, V38, P25
[6]   A continuous time-cost tradeoff problem with multiple milestones and completely ordered jobs [J].
Choi, Byung-Cheon ;
Park, Myoung-Ju .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2015, 244 (03) :748-752
[7]   Complexity results for the linear time-cost tradeoff problem with multiple milestones and completely ordered jobs [J].
Choi, Byung-Cheon ;
Chung, Jibok .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2014, 236 (01) :61-68
[8]   Complexity of the discrete time-cost tradeoff problem for project networks [J].
De, P ;
Dunne, EJ ;
Ghosh, JB ;
Wells, CE .
OPERATIONS RESEARCH, 1997, 45 (02) :302-306
[9]  
Deckstein D, 2011, SPIEGEL ONLINE
[10]  
DEMEULEMEESTER EL, 2002, PROJECT SCHEDULING R