Multimode time-cost-robustness trade-off project scheduling problem under uncertainty

被引:6
作者
Li, Xue [1 ]
He, Zhengwen [1 ]
Wang, Nengmin [1 ]
Vanhoucke, Mario [2 ]
机构
[1] Xi An Jiao Tong Univ, Sch Management, Xian 710049, Peoples R China
[2] Univ Ghent, Fac Econ & Business Adm, B-9000 Ghent, Belgium
基金
中国国家自然科学基金; 中国博士后科学基金;
关键词
Project scheduling problem; Multiobjective optimization model; Trade-off; Epsilon-constraint method; Genetic algorithm; BI-OBJECTIVE MODEL; MULTIPLE MILESTONES; OPTIMIZATION; ALGORITHM; CONSTRAINTS;
D O I
10.1007/s10878-020-00636-7
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
The time/cost trade-off problem is a well-known project scheduling problem that has been extensively studied. In recent years, many researchers have begun to focus on project scheduling problems under uncertainty to cope with uncertain factors, such as resource idleness, high inventory, and missing deadlines. To reduce the disturbance from uncertain factors, the aim of robust scheduling is to generate schedules with time buffers or resource buffers, which are capped by project makespan and project cost. This paper addresses a time-cost-robustness trade-off project scheduling problem with multiple activity execution modes under uncertainty. A multiobjective optimization model with three objectives (makespan minimization, cost minimization, and robustness maximization) is constructed and three propositions are proposed. An epsilon-constraint method-based genetic algorithm along with three improvement measures is designed to solve this NP-hard problem and to develop Pareto schedule sets, and a large-scale computational experiment on a randomly generated dataset is performed to validate the effectiveness of the proposed algorithm and the improvement measures. The final sensitivity analysis of three key parameters shows their distinctive influences on the three objectives, according to which several suggestions are given to project managers on the effective measures to improve the three objectives.
引用
收藏
页码:1173 / 1202
页数:30
相关论文
共 57 条
[1]   Network decomposition-based benchmark results for the discrete time-cost tradeoff problem [J].
Akkan, C ;
Drexl, A ;
Kimms, A .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 165 (02) :339-358
[2]   A bi-objective model for robust resource-constrained project scheduling [J].
Al-Fawzan, MA ;
Haouari, M .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2005, 96 (02) :175-187
[3]   Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach [J].
Azaron, Amir ;
Tavakkoli-Moghaddam, Reza .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2007, 180 (03) :1186-1200
[4]   Multi-mode resource constrained multi-project scheduling and resource portfolio problem [J].
Besikci, Umut ;
Bilge, Umit ;
Ulusoy, Gunduz .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2015, 240 (01) :22-31
[5]   SCHEDULING SUBJECT TO RESOURCE CONSTRAINTS - CLASSIFICATION AND COMPLEXITY [J].
BLAZEWICZ, J ;
LENSTRA, JK ;
KAN, AHGR .
DISCRETE APPLIED MATHEMATICS, 1983, 5 (01) :11-24
[6]   Lawler's minmax cost problem under uncertainty [J].
Brauner, Nadia ;
Finke, Gerd ;
Shafransky, Yakov .
JOURNAL OF COMBINATORIAL OPTIMIZATION, 2017, 34 (01) :31-46
[7]   A linear time-cost tradeoff problem with multiple milestones under a comb graph [J].
Choi, Byung-Cheon ;
Kang, Changmuk .
JOURNAL OF COMBINATORIAL OPTIMIZATION, 2019, 38 (02) :341-361
[8]   Complexity results for the linear time-cost tradeoff problem with multiple milestones and completely ordered jobs [J].
Choi, Byung-Cheon ;
Chung, Jibok .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2014, 236 (01) :61-68
[9]   Recoverable robust timetabling for single delay: Complexity and polynomial algorithms for special cases [J].
Cicerone, Serafino ;
D'Angelo, Gianlorenzo ;
Di Stefano, Gabriele ;
Frigioni, Daniele ;
Navarra, Alfredo .
JOURNAL OF COMBINATORIAL OPTIMIZATION, 2009, 18 (03) :229-257
[10]   THE DISCRETE TIME-COST TRADEOFF PROBLEM REVISITED [J].
DE, P ;
DUNNE, EJ ;
GHOSH, JB ;
WELLS, CE .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1995, 81 (02) :225-238