A note: Maximizing the weighted number of just-in-time jobs on a proportionate flowshop

被引:18
作者
Gerstl, Enrique [1 ,2 ]
Mor, Baruch [3 ]
Mosheiov, Gur [1 ]
机构
[1] Hebrew Univ Jerusalem, Sch Business Adm, IL-91905 Jerusalem, Israel
[2] Jerusalem Coll Technol, Sch Ind Engn, Jerusalem, Israel
[3] Ariel Univ, Dept Econ & Business Adm, Ariel, Israel
基金
以色列科学基金会;
关键词
Scheduling; Proportionate flowshop; Just-in-Time; COMPLETION-TIME; MACHINE SPEEDS; SHOP;
D O I
10.1016/j.ipl.2014.09.004
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
In most cases, an extension of a polynomial time solution of a scheduling problem on a single machine to a proportionate flowshop leads to a similar (polynomial time) solution. One of the rare cases where the problem becomes hard, is that of maximizing the weighted number of Just-in-Time jobs on a proportionate flowshop. We introduce a (pseudo-polynomial) solution algorithm for this problem, which is faster by a factor of n than the algorithm published in the literature. We also introduce a (polynomial time) solution algorithm for the "no-wait" proportionate flowshop. (C) 2014 Elsevier B.V. All rights reserved.
引用
收藏
页码:159 / 162
页数:4
相关论文
共 13 条
[1]   Minimizing the total weighted completion time in a two-machine proportionate flow shop with different machine speeds [J].
Choi, BC ;
Yoon, SH ;
Chung, SJ .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2006, 44 (04) :715-728
[2]   Minimizing maximum completion time in a proportionate flow shop with one machine of different speed [J].
Choi, Byung-Cheon ;
Yoon, Suk-Hun ;
Chung, Sung-Jin .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2007, 176 (02) :964-974
[3]   SEQUENCING 1 STATE-VARIABLE MACHINE - SOLVABLE CASE OF TRAVELING SALESMAN PROBLEM [J].
GILMORE, PC ;
GOMORY, RE .
OPERATIONS RESEARCH, 1964, 12 (05) :655-&
[4]   The three-machine proportionate flow shop problem with unequal machine speeds [J].
Hou, SX ;
Hoogeveen, H .
OPERATIONS RESEARCH LETTERS, 2003, 31 (03) :225-231
[5]   Single machine scheduling to minimize the number of early and tardy jobs [J].
Lann, A ;
Mosheiov, G .
COMPUTERS & OPERATIONS RESEARCH, 1996, 23 (08) :769-781
[6]   OPTIMAL SEQUENCING OF A SINGLE MACHINE SUBJECT TO PRECEDENCE CONSTRAINTS [J].
LAWLER, EL .
MANAGEMENT SCIENCE SERIES A-THEORY, 1973, 19 (05) :544-546
[7]   N JOB, ONE MACHINE SEQUENCING ALGORITHM FOR MINIMIZING THE NUMBER OF LATE JOBS [J].
MOORE, JM .
MANAGEMENT SCIENCE, 1968, 15 (01) :102-109
[8]   Review of the Ordered and Proportionate Flow Shop Scheduling Research [J].
Panwalkar, S. S. ;
Smith, Milton L. ;
Koulamas, Christos .
NAVAL RESEARCH LOGISTICS, 2013, 60 (01) :46-55
[9]  
Pinedo ML, 2012, SCHEDULING: THEORY, ALGORITHMS, AND SYSTEMS, FOURTH EDITION, P1, DOI 10.1007/978-1-4614-2361-4
[10]   THE 3-MACHINE NO-WAIT FLOWSHOP IS NP-COMPLETE [J].
ROCK, H .
JOURNAL OF THE ACM, 1984, 31 (02) :336-345