Assessing and allocating the financial viability risk factors in public-private partnership wastewater treatment plant projects

被引:18
|
作者
El-Kholy, Amr Metwally [1 ]
Akal, Ahmed Yousry [2 ]
机构
[1] Beni Suef Univ, Fac Engn, Dept Civil Engn, Bani Suwayf, Egypt
[2] Higher Inst Engn & Technol, Dept Civil Engn, Kafrelsheikh, Egypt
关键词
Financial viability; Public private partnership (PPP); Wastewater treatment plants (WWTPs); Risks; Allocation; Fuzzy synthetic evaluation (FSE); Developing countries; CAPITAL STRUCTURE OPTIMIZATION; DEVELOPING-COUNTRIES; SUPPLY PROJECTS; OPERATE; BUILD; PPP; CHINA; FRAMEWORK; RANKING; MODEL;
D O I
10.1108/ECAM-05-2020-0373
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Purpose This research investigates the financial viability risk factors that threaten the private investor's economic scheme in the public private partnership (PPP) wastewater treatment plant (WWTP) projects in Egypt. The aims of this study are to: (1) illustrate and cluster the financial viability risk factors in accordance with the PPP WWTP projects' nature, (2) assess the risk factors' criticality degrees according to their severity and frequency levels of the financial viability, and (3) pinpoint the suited allocation of the financial viability risk factors between the public and private parties. Design/methodology/approach Relying on the previous analysts' endeavors, the questionnaire method, the fuzzy synthetic evaluation approach and the hypothetical normal distribution curve model; the severity, frequency, criticality and allocation preference of 32 financial viability risk factors were assessed from 12 Egyptian PPP experts. Findings The data analysis yielded that foreign exchange risk, currency risk/inflation, license risk, construction cost-overrun and late site handover are the key factors in arising the financial viability risk issue in the PPP WWTP projects. Considering the discussion of these key risks, the study summarized that the financial viability's key risk factors are notably be affected by the economic, political and administrative circumstances of the host county. Additionally, the inflation lesion was found to be the core reason of most of the key risk factors. Originality/value This research originality stems from its contribution to address the gab in the PPP risk assessment literature of the concessionaire's financial viability in the WWTP projects in a country of developing economy as Egypt. This, first, enriches the scholarly based knowledge of the PPP projects' risk analysts of the developing countries. Accordingly, it moves the current PPP risk assessment research further to deeply apprehend these markets' risks. Second, it equips the policymakers in the public and private sectors of such projects with a map that clarifies their assigned risk factors and the responsibilities that each party should bear to generate a mutual stable investment environment for achieving their aims successfully. This, indeed, paves the way for more private investments to be involved in the developing markets' PPP projects with a profitable satisfactory level for the private concessionaire. In the same vein, more WWTP projects, which are highly needed for the public sector and its people, are executed.
引用
收藏
页码:3014 / 3040
页数:27
相关论文
共 50 条
  • [21] A South African Public-Private Partnership HIV Treatment Model: Viability and Success Factors
    Igumbor, Jude
    Pascoe, Sophie
    Rajap, Shuabe
    Townsend, Wendy
    Sargent, John
    Darkoh, Ernest
    PLOS ONE, 2014, 9 (10):
  • [22] Managing Critical Risks Affecting the Financial Viability of Public-Private Partnership Projects: Case Study of Toll Road Projects in Vietnam
    Anh Nguyen
    Mollik, Abu
    Chih, Ying-Yi
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2018, 144 (12)
  • [23] Investment decision model of wastewater treatment public-private partnership projects based on value for money
    Yu, Shunkun
    Dai, Tong
    Yu, Yang
    Zhang, Jinying
    WATER AND ENVIRONMENT JOURNAL, 2021, 35 (01) : 322 - 334
  • [24] Identifying Factors Affecting the Sustainability of Water Environment Treatment Public-Private Partnership Projects
    Li, Huimin
    Xia, Qing
    Wen, Shiping
    Wang, Lunyan
    Lv, Lelin
    ADVANCES IN CIVIL ENGINEERING, 2019, 2019
  • [25] CORPORATE FINANCING OF PUBLIC-PRIVATE PARTNERSHIP PROJECTS: ASSESSMENT OF FINANCIAL OPPORTUNITIES AND RISKS
    Shuliuk, B.
    FINANCIAL AND CREDIT ACTIVITY-PROBLEMS OF THEORY AND PRACTICE, 2021, 3 (38): : 78 - 85
  • [26] The execution of public-private partnership projects in the UAE
    Dulaimi, Mohammed Fadhil
    Alhashemi, Mohamed
    Ling, Florence Yean Yng
    Kumaraswamy, Mohan
    CONSTRUCTION MANAGEMENT AND ECONOMICS, 2010, 28 (04) : 393 - 402
  • [27] Liability of Foreignness in Public-Private Partnership Projects
    Kong, Zijiong
    Ma, Hanyang
    Lv, Kangjuan
    Shi, Jonathan J. J.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2023, 149 (09)
  • [28] Discounting for public-private partnership projects in China
    Luo, Lanlan
    Zou, Ziran
    Chen, Shou
    ECONOMIC MODELLING, 2021, 98 : 218 - 226
  • [29] Negative factors in implementing public-private partnership in Indian road projects
    Malek, Mohammedshakil S.
    Gundaliya, P. J.
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2023, 23 (02) : 234 - 242
  • [30] Public-Private Partnership Highway Projects: Identifying Project Selection Factors
    Fathi, Medya
    Shrestha, Pramen P.
    JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2023, 15 (01)