Planned lead times optimization for multi-level assembly systems under uncertainties

被引:17
作者
Ben-Ammar, Oussama [1 ]
Dolgui, Alexandre [1 ]
Wu, Desheng Dash [2 ]
机构
[1] IMT Atlantique, LS2N, UMR CNRS 6004, 4 Rue Alfred Kastler,BP 20722, F-44307 Nantes, France
[2] Univ Toronto, Risklab, Toronto, ON M5S 3G3, Canada
来源
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE | 2018年 / 78卷
关键词
Multi-level assembly systems; Assemble-to-order; Assembly contracting; Stochastic lead-times; Planned lead times optimization; Stochastic modeling; Branch and bound; SERIAL PRODUCTION SYSTEMS; SUPPLY-CHAIN UNCERTAINTY; OF-THE-ART; COMPONENT PROCUREMENT; PROGRAMMING APPROACH; INVENTORY CONTROL; MRP ENVIRONMENTS; TARDINESS COSTS; MANAGEMENT; LEADTIMES;
D O I
10.1016/j.omega.2017.11.004
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Planned lead times are crucial parameters in management of supply networks that continue to be more and more extended with multiple levels of inventory of components and uncertainties. The object of this study is the problem of determining planned lead times in multi-level assembly systems with stochastic lead times of different partners of supply chains. A general probabilistic model with a recursive procedure to calculate all the necessary distributions of probability is proposed. A Branch and Bound algorithm is developed for this model to determine planned order release dates for components at the last level of a BOM which minimize the sum of inventory holding and backlogging costs. Experimental results show the behavior of the proposed model and optimisation algorithm for different numbers of components at the last level of the BOM and for different numbers of levels and values of holding and backlogging costs. The model and algorithm can be used for assembly contracting in an assembly to order environment under lead time uncertainty. (C) 2017 Elsevier Ltd. All rights reserved.
引用
收藏
页码:39 / 56
页数:18
相关论文
共 58 条
[1]   A bibliography of non-deterministic lot-sizing models [J].
Aloulou, Mohamed Ali ;
Dolgui, Alexandre ;
Kovalyov, Mikhail Y. .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2014, 52 (08) :2293-2310
[2]  
[Anonymous], INT J PRODUCTION RES
[3]  
[Anonymous], 2004, Knapsack Problems, DOI DOI 10.1007/978-3-540-24777-710
[4]   Inventory control in a multi-supplier system [J].
Arda, Yasemin ;
Hennet, Jean-Claude .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2006, 104 (02) :249-259
[5]   Setting Planned Leadtimes in Customer-Order-Driven Assembly Systems [J].
Atan, Zumbul ;
de Kok, Ton ;
Dellaert, Nico P. ;
van Boxel, Richard ;
Janssen, Fred .
M&SOM-MANUFACTURING & SERVICE OPERATIONS MANAGEMENT, 2016, 18 (01) :122-140
[6]   Impact of lead time variability in supply chain risk management [J].
Bandaly, Dia ;
Satir, Ahmet ;
Shanker, Latha .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2016, 180 :88-100
[7]  
Berlec T, 2008, STROJ VESTN-J MECH E, V54, P308
[8]   Component procurement and end product assembly in an uncertain supply and demand environment [J].
Bollapragada, Ramesh ;
Kuppusamy, Saravanan ;
Rao, Uday S. .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2015, 53 (03) :969-982
[9]   Component replenishment planning for a single-level assembly system under random lead times: A chance constrained programming approach [J].
Borodin, Valeria ;
Dolgui, Alexandre ;
Hnaien, Faicel ;
Labadie, Nacima .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2016, 181 :79-86
[10]   Inventory management with variable lead-time dependent procurement cost [J].
Chandra, Charu ;
Grabis, Janis .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2008, 36 (05) :877-887