A buffer control method for top-down project control

被引:48
作者
Martens, Annelies [1 ]
Vanhoucke, Mario [1 ,2 ,3 ]
机构
[1] Univ Ghent, Fac Econ & Business Adm, Tweekerkenstr 2, B-9000 Ghent, Belgium
[2] Vlerick Business Sch, Technol & Operat Management, Reep 1, B-9000 Ghent, Belgium
[3] UCL, UCL Sch Management, 1 Canada Sq, London E14 5AA, England
关键词
Project management; Schedule control; Earned value management (EVM); Simulation; Project buffer; EARNED VALUE MANAGEMENT; SENSITIVITY; PERFORMANCE; INFORMATION; DURATION; LIMITS;
D O I
10.1016/j.ejor.2017.03.034
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Timely completion of projects is an important factor for project success. However, projects often exceed their predefined deadline, which results in a late project delivery and an increase in the total project cost. In order to increase the probability of timely completion, a project buffer can be planned at the end of a project. During project execution, an assessment of the total buffer consumption at the project completion date can be made in order to periodically monitor the project progress. When the expected buffer consumption is higher than 100%, the project deadline is expected to be exceeded and the project manager should take corrective actions to get the project back on track. In this paper, a new buffer monitoring approach is introduced, which sets tolerance limits for Earned Value Management/Earned Schedule (EVM/ES) schedule performance metrics by allocating the project buffer over the different project phases. The purpose of these tolerance limits is to provide the project manager with accurate and reliable information on the expected project outcome during the project execution. A computational study is carried out to assess the performance of the proposed approach and to compare its performance with traditional buffer consumption monitoring procedures. Additionally, existing performance metrics for tolerance limits have been put into a hypothesis testing framework, and new metrics have been developed in order to fill the detected gaps in performance measurement. Results have shown that the proposed tolerance limits improve the performance of the monitoring phase, especially for parallel projects. Consequently, the underperformance of EVM/ES for parallel projects is mitigated by these limits. (C) 2017 Elsevier B.V. All rights reserved.
引用
收藏
页码:274 / 286
页数:13
相关论文
共 45 条
[1]   FITTING BETA-DISTRIBUTIONS BASED ON SAMPLE DATA [J].
ABOURIZK, SM ;
HALPIN, DW ;
WILSON, JR .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1994, 120 (02) :288-305
[2]   Monitoring project duration and cost in a construction project by applying statistical quality control charts [J].
Aliverdi, Reza ;
Naeni, Leila Moslemi ;
Salehipour, Amir .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2013, 31 (03) :411-423
[3]  
Anbari F.T., 2003, PROJ MANAG J, V34, P12, DOI [10.1109/EMR.2004.25113, DOI 10.1177/875697280303400403, 10.1177/875697280303400403]
[4]  
[Anonymous], 2004, GUID PROJ MAN BOD KN
[5]  
[Anonymous], CROSSTALK J DEFENSE
[6]  
Bauch G.T., 2001, PROJ MANAG J, V32, P37
[7]   Developing activity duration specification limits for effective project control [J].
Bowman, R. Alan .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2006, 174 (02) :1191-1204
[8]   A multivariate approach for top-down project control using earned value management [J].
Colin, Jeroen ;
Martens, Annelies ;
Vanhoucke, Mario ;
Wauters, Mathieu .
DECISION SUPPORT SYSTEMS, 2015, 79 :65-76
[9]   Developing a framework for statistical process control approaches in project management [J].
Colin, Jeroen ;
Vanhoucke, Mario .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2015, 33 (06) :1289-1300
[10]   A comparison of the performance of various project control methods using earned value management systems [J].
Colin, Jeroen ;
Vanhoucke, Mario .
EXPERT SYSTEMS WITH APPLICATIONS, 2015, 42 (06) :3159-3175