EVALUATING PERFORMANCE OF CRITICAL CHAIN PROJECT MANAGEMENT TO MITIGATE DELAYS BASED ON DIFFERENT SCHEDULE NETWORK COMPLEXITIES

被引:0
|
作者
Su, Yi [1 ]
Lucko, Gunnar [1 ]
Thompson, Richard C., Jr. [1 ]
机构
[1] Catholic Univ Amer, Dept Civil Engn, Construct Engn & Management Program, Washington, DC 20064 USA
来源
2016 WINTER SIMULATION CONFERENCE (WSC) | 2016年
基金
美国国家科学基金会;
关键词
D O I
暂无
中图分类号
TP301 [理论、方法];
学科分类号
081202 ;
摘要
The Critical Chain Project Management (CCPM) method uses both project and feeder buffers in network schedules to act as cushions that absorb delays. These buffers are periods that are placed at the ends of critical or non-critical paths within the schedule. But how CCPM performs for probabilistic schedules has barely been studied systematically. It is hypothesized that the complexity of the networks influences how efficiently allocated buffers can fulfill their protective role. This paper therefore explores the relationship between complexity indices and the delay-mitigating performance of CCPM. Its contribution to the body of knowledge is twofold: First, schedule network complexity indices are reviewed and a schedule network graphing module is developed, which identifies the critical chain and buffer locations. Second, CCPM is applied to networks of different complexity with probabilistic durations. Their performance is measured in Monte Carlo simulations to evaluate the efficacy of buffer allocation under various different scenarios.
引用
收藏
页码:3314 / 3324
页数:11
相关论文
共 50 条
  • [1] Critical chain, project schedule management based on Bayesian Network model
    College of Economics and Management, Tongji University, Shanghai
    200092, China
    Tongji Daxue Xuebao, 10 (1606-1612):
  • [2] PROJECT SCHEDULE MANAGEMENT BASED ON CRITICAL CHAIN METHOD
    Yu, Lianghui
    Jia, Ling
    Zhou, Dandan
    ICIM 2010: PROCEEDINGS OF THE TENTH INTERNATIONAL CONFERENCE ON INDUSTRIAL MANAGEMENT, 2010, : 269 - 273
  • [3] Fuzzy optimization of construction engineering project schedule based on critical chain management
    Liu, J. (Liujb71@sina.cn), 2013, Universitas Ahmad Dahlan, Jalan Kapas 9, Semaki, Umbul Harjo,, Yogiakarta, 55165, Indonesia (11):
  • [4] Research on Software Project Schedule Based on Critical Chain
    Xu Huihua
    Wan Li
    Xue Song
    2019 5TH INTERNATIONAL CONFERENCE ON ENERGY MATERIALS AND ENVIRONMENT ENGINEERING, 2019, 295
  • [5] Dynamic safety evaluating based on project network schedule
    Xu, Chengxiang
    Zhang, Jianshe
    Wuhan Ligong Daxue Xuebao/Journal of Wuhan University of Technology, 2002, 24 (02):
  • [6] Schedule of supply chain management project based on TOC
    Leng Kaijun
    Shi Wen
    Hu Xuejun
    Pan Lin
    JOURNAL OF INTELLIGENT & FUZZY SYSTEMS, 2017, 33 (05) : 2801 - 2809
  • [7] Research on Critical Chain Identification Methods of Project Schedule Management in China
    Li, Qing-hua
    2018 2ND INTERNATIONAL CONFERENCE ON ADVANCES IN MANAGEMENT SCIENCE AND ENGINEERING (AMSE 2018), 2018, 292 : 75 - 78
  • [8] Application research on the critical chain technology in engineering project schedule management
    Zhang, Ai-Lin
    Wang, Li-Xia
    Information Technology Journal, 2013, 12 (17) : 4196 - 4199
  • [9] Identifying the critical chain in the schedule of random network based on GERTs
    Shi, Qian
    Gong, Ting
    Shi, Q. (qianshi@mail.tongji.edu.cn), 1600, Systems Engineering Society of China (32): : 1531 - 1536
  • [10] The Analysis of Bank Mobile Payment Project's Schedule Management Based on Improved Critical Chain Method
    Cheng, Peng
    Liang, Song
    PROCEEDINGS OF THE 2ND INTERNATIONAL SYMPOSIUM ON BUSINESS CORPORATION AND DEVELOPMENT IN SOUTH-EAST AND SOUTH ASIA UNDER B&R INITIATIVE (ISBCD 2017), 2017, 42 : 20 - 24