Comparison of predicted and actual states in tunnels: lessons to be learned from the Gerede Water Transmission Tunnel, Turkey

被引:2
作者
Apaydin, Ahmet [1 ]
机构
[1] Giresun Univ, Dept Civil Engn, TR-28200 Giresun, Turkey
关键词
Advance rates - Earth pressure balance shield - Groundwater pressure - High water pressure - Hydrogeological conditions - Project reports - Tunnel boring machines - Water transmission;
D O I
10.1144/qjegh2020-060
中图分类号
P5 [地质学];
学科分类号
0709 ; 081803 ;
摘要
The Gerede Tunnel is a large inter-basin project in Turkey. As with many long tunnels, some of the predictions in the project report and the tender contract have not been realized. Completion of the tunnel has been delayed for more than twice the time given in the tender contract. Unexpectedly complex geological-tectonic-hydrogeological conditions and the selection of tunnel-boring machines (TBMs) are the main reasons for this long delay. There were some discrepancies between the predicted and actual geology. The groundwater pressure encountered was much higher than expected. Plastic clays in the limestone and breccia and loose agglomerates with a high water pressure in the faults decreased the advance rate and led to several long stoppages. One of the three double-shield TBMs became stuck in the tunnel and could not be recovered. The last quarter of the tunnel was excavated more slowly, but without severe problems, by a modified earth pressure balance shield TBM. As a result, the TBM type, drive direction, length, route, cost and completion date of the Gerede Tunnel have all changed.
引用
收藏
页数:10
相关论文
共 26 条
  • [1] Aguilar-Téllez MA, 2012, GEOTECHNICAL ASPECTS OF UNDERGROUND CONSTRUCTION IN SOFT GROUND, 7TH INTERNATIONAL SYMPOSIUM, P3
  • [2] Assessment of the factors affecting the advance rate of the Tunnel Gerede, the longest and one of the most problematic water transmission tunnels of Turkey
    Alp, Murat
    Apaydin, Ahmet
    [J]. TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2019, 89 : 157 - 169
  • [3] Water inflow into tunnels: assessment of the Gerede water transmission tunnel (Turkey) with complex hydrogeology
    Apaydin, Ahmet
    Korkmaz, Nur
    Ciftci, Donmez
    [J]. QUARTERLY JOURNAL OF ENGINEERING GEOLOGY AND HYDROGEOLOGY, 2019, 52 (03) : 346 - 359
  • [4] Apaydn A., 2019, DSI TEKNIK BULTENI, V129, P27
  • [5] Bahadorbeygi D., 2009, ISRM REG S EUROCK 20, P5
  • [6] A study for predicting the maximum gas temperature beneath ceiling in sealing tactics against tunnel fire
    Chen, Changkun
    Zhang, Yulun
    Lei, Peng
    Jiao, Weibing
    [J]. TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2020, 98 (98)
  • [7] Dalgic S., 1991, TMMOB JEOLOJI MUHEND, V51, P36
  • [8] Davies T.P., 1981, 676 TRANSP ROAD RES
  • [9] Dowding C.H., 1976, P RAP EXC TUNN C 14, P19
  • [10] Fahmdanesha S., 2014, INDIAN J SCI RES, V9, P137, DOI [10.5958/2250-0138.2014.00022.4, DOI 10.5958/2250-0138.2014.00022.4]