Monitoring and analysis of long-term prestress losses in post-tensioned concrete beams

被引:55
作者
Guo, Tong [1 ]
Chen, Zheheng [1 ]
Lu, Shuo [1 ]
Yao, Ruigen [2 ]
机构
[1] Southeast Univ, Sch Civil Engn, Minist Educ, Key Lab Concrete & Prestressed Concrete Struct, Nanjing, Jiangsu, Peoples R China
[2] Southeast Univ, Int Inst Urban Syst Engn, Nanjing, Jiangsu, Peoples R China
关键词
Long-term prestress loss; Post-tensioned concrete beam; Monitoring; Prediction model; Shrinkage; Creep; BRIDGE; SENSORS; STRESS; PREDICTION; GPS;
D O I
10.1016/j.measurement.2017.07.057
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In order to investigate the long-term prestress losses in post-tensioned concrete beams, time-dependent responses of eight post-tensioned concrete beams were monitored for more than one year. Load cells, vibrating wire strain gauges (VWSGs) and elasto-magnetic (EM) sensors were used jointly to measure the tendon forces at beam ends, the prestress losses due to concrete creep and shrinkage and the total prestress losses along tendons, respectively. In this way, the prestress losses due to different factors and at different locations were observed more accurately. Based on the monitored data, the influence of tendon layout, reinforcement ratio, duct grouting, stress level and jacking sequence, etc., on long-term prestress losses were analyzed. An improved model for predicting the time-dependent prestress losses was thus proposed, in which non-prestressed steel and the interaction among the shrinkage, creep of concrete and steel stress relaxation were taken into account. The proposed model has higher accuracy as compared with existing models in specifications, and the maximum difference between test and predicted results is within 10%.
引用
收藏
页码:573 / 581
页数:9
相关论文
共 46 条
[1]  
Ahlborn T. M., 2000, MNRC200032 MINN DEP
[2]   Full-scale testing of prestressed concrete bridge girders [J].
Ahlborn, TM ;
Shield, CK ;
French, CW .
EXPERIMENTAL TECHNIQUES, 1997, 21 (01) :33-35
[3]  
[Anonymous], 1992, ACI Manual of Concrete Practice, Part 5, P1
[4]  
[Anonymous], 2006, THESIS
[5]  
[Anonymous], 2004, LRFD BRIDG DES SPEC
[6]  
[Anonymous], 1993, CEB FIP MOD COD 1990
[7]  
[Anonymous], 2002, Standard Specifications for Highway Bridges
[8]   Comparison of prestress losses for a prestress concrete bridge made with high-performance concrete [J].
Barr, P. J. ;
Kukay, B. M. ;
Halling, M. W. .
JOURNAL OF BRIDGE ENGINEERING, 2008, 13 (05) :468-475
[9]  
Bazant Z.P., 1972, ACI J, V69, P212
[10]  
Bazant Z.P., 2010, ACI Concrete International, V32, P44