Performance study and application of new coal-fired boiler flue gas heat recovery system

被引:75
作者
Wei, Maolin [1 ]
Zhao, Xiling [2 ]
Fu, Lin [2 ,3 ]
Zhang, Shigang [1 ]
机构
[1] Tsinghua Planning & Design Inst, Dept Energy Planning & Design, Beijing, Peoples R China
[2] Tsinghua Univ, Sch Architecture, Beijing, Peoples R China
[3] Tsinghua Univ, Beijing Key Lab Indoor Air Qual Evaluat & Contro, Beijing, Peoples R China
基金
中国国家自然科学基金;
关键词
Absorption heat pump; Coal-fired boiler; Direct-contact heat exchanger; Engineering application analysis; Flue gas heat recovery; LOW-PRESSURE ECONOMIZER; WASTE HEAT; THERMODYNAMIC ANALYSIS; DESIGN; PUMP; SIMULATION;
D O I
10.1016/j.apenergy.2016.11.132
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
The recovery of heat from the flue gas is an effective way to improve the thermal efficiency of a boiler. In a coal-fired boiler with wet-desulphurization, a portion of the flue gas thermal energy is used for the latent heat process, which leads to temperature reduction and humidity increase. Although it still contains significant heat, flue gas without sulfur cannot be further utilized; as such, in conventional systems, it is directly exhausted. This paper proposes a new system that utilizes the remaining heat in sulfur reduced flue gas, where direct-contact heat transfer and absorption technologies are used to even further reduce the exhausted flue gas temperature. Here, not only is the heat recovered, but waste water is also reused as the make-up water in the flue gas desulphurization (FGD) tower. An engineering application analysis provides a detailed account of the system thermodynamic characteristics, economic profitability, and pollutant emission reduction effects. The results show that the boiler efficiency improves by 3.2 percentage point when the exhaust temperature decreases to 39 degrees C. Also, the pressure drop in the heat exchanger remains below 400 Pa, which results in low extra electricity consumption. The direct cooling treatment removes 59% of sulfur dioxide and 8.8% of nitrogen dioxide. The investment is 28.8 million RMB and the annual net revenue is 7.4 million RMB, with a static payback period of 3.8 years; as such, it is commercially viable. In summary, the new system simultaneously saves energy, saves water, and reduces pollutant emissions. (C) 2016 Elsevier Ltd. All rights reserved.
引用
收藏
页码:121 / 129
页数:9
相关论文
共 29 条
[1]   Towards an intermittency-friendly energy system: Comparing electric boilers and heat pumps in distributed cogeneration [J].
Blarke, Morten B. .
APPLIED ENERGY, 2012, 91 (01) :349-365
[2]   Condensing boiler applications in the process industry [J].
Chen, Qun ;
Finney, Karen ;
Li, Hanning ;
Zhang, Xiaohui ;
Zhou, Jue ;
Sharifi, Vida ;
Swithenbank, Jim .
APPLIED ENERGY, 2012, 89 (01) :30-36
[3]  
Copen J.H., PRINCIPLES FLUE GAS
[4]   Efficiency improvement strategies for the feedwater heaters network designing in supercritical coal-fired power plants [J].
Espatolero, Sergio ;
Romeo, Luis M. ;
Cortes, Cristobal .
APPLIED THERMAL ENGINEERING, 2014, 73 (01) :449-460
[5]   Investigation on the off-design performances of flue gas pre-dried lignite-fired power system integrated with waste heat recovery at variable external working conditions [J].
Han, Xiaoqu ;
Liu, Ming ;
Zhai, Mengxu ;
Chong, Daotong ;
Yan, Junjie ;
Xiao, Feng .
ENERGY, 2015, 90 :1743-1758
[6]   Simulation study on lignite-fired power system integrated with flue gas drying and waste heat recovery - Performances under variable power loads coupled with off-design parameters [J].
Han, Xiaoqu ;
Liu, Ming ;
Wang, Jinshi ;
Yan, Junjie ;
Liu, Jiping ;
Xiao, Feng .
ENERGY, 2014, 76 :406-418
[7]  
[吕明 Lu Ming], 2010, [动力工程学报, Journal of Power Engineering], V30, P695
[8]   Analysis of the use of waste heat obtained from coal-fired units in Organic Rankine Cycles and for brown coal drying [J].
Lukowicz, Henryk ;
Kochaniewicz, Andrzej .
ENERGY, 2012, 45 (01) :203-212
[9]   Experimental investigation on heat recovery from diesel engine exhaust using finned shell and tube heat exchanger and thermal storage system [J].
Pandiyarajan, V. ;
Pandian, M. Chinna ;
Malan, E. ;
Velraj, R. ;
Seeniraj, R. V. .
APPLIED ENERGY, 2011, 88 (01) :77-87
[10]   New configurations of a heat recovery absorption heat pump integrated with a natural gas boiler for boiler efficiency improvement [J].
Qu, Ming ;
Abdelaziz, Omar ;
Yin, Hongxi .
ENERGY CONVERSION AND MANAGEMENT, 2014, 87 :175-184