Automated BIM schedule generation approach for solving time-cost trade-off problems

被引:20
|
作者
ElMenshawy, Mohamed [1 ]
Marzouk, Mohamed [1 ]
机构
[1] Cairo Univ, Cairo, Egypt
关键词
Building information modeling; Schedule generation; Optimization; Genetic algorithm; Time-cost trade-off; CONSTRUCTION; ALGORITHM;
D O I
10.1108/ECAM-08-2020-0652
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Purpose Nowadays, building information modeling (BIM) represents an evolution in the architecture, engineering and construction (AEC) industries with its various applications. BIM is capable to store huge amounts of information related to buildings which can be leveraged in several areas such as quantity takeoff, scheduling, sustainability and facility management. The main objective of this research is to establish a model for automated schedule generation using BIM and to solve the time-cost trade-off problem (TCTP) resulting from the various scenarios offered to the user. Design/methodology/approach A model is developed to use the quantities exported from a BIM platform, then generate construction activities, calculate the duration of each activity and finally the logic/sequence is applied in order to link the activities together. Then, multiobjective optimization is performed using nondominated sorting genetic algorithm (NSGA-II) in order to provide the most feasible solutions considering project duration and cost. The researchers opted NSGA-II because it is one of the well-known and credible algorithms that have been used in many applications, and its performances were tested in several comparative studies. Findings The proposed model is capable to select the near-optimum scenario for the project and export it to Primavera software. A case study is worked to demonstrate the use of the proposed model and illustrate its main features. Originality/value The proposed model can provide a simple and user-friendly model for automated schedule generation of construction projects. In addition, opportunities related to the interface between an automated schedule generation model and Primavera software are enabled as Primavera is one of the most popular and common schedule software solutions in the construction industry. Furthermore, it allows importing data from MS Excel, which is used to store activities data in the different scenarios. In addition, there are numerous solutions, each one corresponds to a certain duration and cost according to the performance factor which often reflects the number of crews assigned to the activity and/or construction method.
引用
收藏
页码:3346 / 3367
页数:22
相关论文
共 50 条
  • [41] A contingency approach for time-cost trade-off in construction projects based on machine learning techniques
    Wang, Peipei
    Wang, Kun
    Huang, Yunhan
    Fenn, Peter
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2024, 31 (11) : 4677 - 4695
  • [42] A Dependent-Chance Programming Model for Fuzzy Time-Cost Trade-off Problem
    Ke, Hua
    Ma, Weimin
    2009 IEEE INTERNATIONAL CONFERENCE ON FUZZY SYSTEMS, VOLS 1-3, 2009, : 2183 - 2186
  • [43] Time-cost trade-off analysis of a priority based assignment problem
    Prabhjot Kaur
    Kalpana Dahiya
    Vanita Verma
    OPSEARCH, 2021, 58 : 448 - 482
  • [44] A crashing-based time-cost trade-off model considering quality cost and contract clauses
    Akin, Firat Dogu
    Polat, Gul
    Turkoglu, Harun
    Damci, Atilla
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2021, 23 (06) : 954 - 963
  • [45] A mixed (continuous plus discrete) time-cost trade-off model considering four different relationships with lag time
    Son, Jaeho
    Hong, TaeHoon
    Lee, Sangyoub
    KSCE JOURNAL OF CIVIL ENGINEERING, 2013, 17 (02) : 281 - 291
  • [46] Pareto Front Particle Swarm Optimizer for Discrete Time-Cost Trade-Off Problem
    Aminbakhsh, Saman
    Sonmez, Rifat
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2017, 31 (01)
  • [47] New Time-Cost Trade-Off Model Considering the Sequence of Alternatives Between Activities
    Kang, Namuk
    Son, Jaeho
    Lee, Seunghyun
    JOURNAL OF ASIAN ARCHITECTURE AND BUILDING ENGINEERING, 2015, 14 (02) : 379 - 386
  • [48] A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
    Fu, Fang
    Zhang, Tao
    PLOS ONE, 2016, 11 (12):
  • [49] Discrete symbiotic organisms search method for solving large-scale time-cost trade-off problem in construction scheduling
    Liu, Dian
    Li, Heng
    Wang, Hongwei
    Qi, Chao
    Rose, Timothy
    EXPERT SYSTEMS WITH APPLICATIONS, 2020, 148
  • [50] A time-cost trade-off model with resource consideration using genetic algorithm
    Chua, DKH
    Chan, WT
    Govindan, K
    CIVIL ENGINEERING SYSTEMS, 1997, 14 (04): : 291 - 311