Economical Design of Utility-Scale Photovoltaic Power Plants With Optimum Availability

被引:55
作者
Moradi-Shahrbabak, Zahra [1 ]
Tabesh, Ahmadreza [1 ]
Yousefi, Gholam Reza [1 ]
机构
[1] Isfahan Univ Technol, Dept Elect & Comp Engn, Esfahan 8415683111, Iran
关键词
Levelized cost of energy (LCOE); photovoltaic (PV) power plants; power system availability; PV energy system reliability; PV plant topology design; technoeconomical analysis; RELIABILITY-ANALYSIS; INVERTERS; OPTIMIZATION; TOPOLOGIES;
D O I
10.1109/TIE.2013.2278525
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
This paper presents an algorithm for the economical design of a utility-scale photovoltaic (PV) power plant via compromising between the cost of energy and the availability of the plant. The algorithm inputs are the plant peak power and the price of inverters with respect to their power ratings. The outputs are the optimum inverter ratings and the interconnection topology of PV panels. This paper introduces the effective levelized cost of energy (LCOE) (ELCOE) index as the core of the proposed design algorithm. ELCOE is an improved index based on the conventional LCOE that includes the availability of a power plant in economical assessments. The conventional LCOE index determines centralized topology (e.g., 1-MW inverter for a 1-MW PV power plant) for minimizing the energy generation cost, whereas based on ELCOE, a multistring topology (e.g., a 1-MW PV plant consists of fifty 20-kW inverters) despite of higher investment cost becomes the economically winning topology. Given the price of commercially available PV inverters at present, the case studies in this paper show that, for 0.1-100-MW PV power plants, the economical ratings of inverters range from 8 to 100 kW. The recently installed PV power plants confirm the feasibility of the calculations based on the suggested algorithm.
引用
收藏
页码:3399 / 3406
页数:8
相关论文
共 25 条
[1]  
[Anonymous], 1991, MH MILITARY HDB
[2]  
[Anonymous], IEEE PHOT SPEC CONF
[3]  
[Anonymous], 1992, RELIABILITY EVALUATI
[4]  
[Anonymous], 2010, ADDR SOL PHOT OP MAI
[5]  
Brenna M., 2010, IEEE POWER ENERGY SO, P1, DOI DOI 10.1109/PES.2010.5589768
[6]  
Campbell M, 2009, IEEE PHOT SPEC CONF, P537
[7]  
Carbone R., 2009, 2009 International Conference on Clean Electrical Power (ICCEP), P760, DOI 10.1109/ICCEP.2009.5211967
[8]   Reliability Estimation of Three Single-Phase Topologies in Grid-Connected PV Systems [J].
Chan, Freddy ;
Calleja, Hugo .
IEEE TRANSACTIONS ON INDUSTRIAL ELECTRONICS, 2011, 58 (07) :2683-2689
[9]  
Deline C., 2010, DEAC3608GO28308 NREL
[10]  
Deline C., 2012, RENEWABLE ENERGY TEC, V1