Comparison of software prediction and measured performance of a grid-connected photovoltaic power plant

被引:17
作者
Palmero-Marrero, Ana [1 ,2 ]
Matos, Jose C. [2 ]
Oliveira, Armando C. [1 ,2 ]
机构
[1] Univ Porto, Dept Mech Engn, P-4100 Oporto, Portugal
[2] Inst Mech Engn & Ind Management INEGI, Oporto, Portugal
关键词
PV SYSTEMS; TEMPERATURE;
D O I
10.1063/1.4935376
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
In this work, the performance of a photovoltaic (PV) installation is assessed. The plant consists of a grid-connected centralized system, where the supplied power is not associated with a particular electricity customer. Operational data from this PV plant, ground-mounted and located in the north of Portugal, are now available for a period of 3 years. The plant is equipped with PV modules (amorphous Si cells), with 60 Wp per module, and a total generating capacity of 124.2 kWp. In this installation, 24 inverters are used. To obtain an accurate prediction of the efficiency and power output, the characteristics of all plant components were introduced in the PVsyst software and TRNSYS software, together with meteorological data: either those collected at a local meteorological station or those provided by Meteonorm. The results obtained through the simulations and the measured output power values were compared. The results showed that both PVsyst and TRNSYS seem to be good tools to predict the annual electrical production of a PV plant, with an average relative difference in the results between both around 2%. In the simulations, parameters like orientation and inclination of the PV modules were analyzed and recommendations for improving the PV system production are given. The results showed that in the annual electrical production, the effect of panel tilt angle is more significant than the effect of panel orientation. (C) 2015 AIP Publishing LLC.
引用
收藏
页数:9
相关论文
共 18 条
[1]  
[Anonymous], 1998, IEC 61724
[2]   A simplified model for the estimation of energy production of PV systems [J].
Aste, Niccolo ;
Del Pero, Claudio ;
Leonforte, Fabrizio ;
Manfren, Massimiliano .
ENERGY, 2013, 59 :503-512
[3]   Performance of grid-tied PV facilities: A case study based on real data [J].
Diez-Mediavilla, M. ;
Dieste-Velasco, M. I. ;
Rodriguez-Amigo, M. C. ;
Garcia-Calderon, T. ;
Alonso-Tristan, C. .
ENERGY CONVERSION AND MANAGEMENT, 2013, 76 :893-898
[4]   Grid-connected photovoltaic power systems: Technical and potential problems-A review [J].
Eltawil, Mohamed A. ;
Zhao, Zhengming .
RENEWABLE & SUSTAINABLE ENERGY REVIEWS, 2010, 14 (01) :112-129
[5]   Design of grid connected PV systems considering electrical, economical and environmental aspects:: A practical case [J].
Fernandez-Infantes, Alberto ;
Contreras, Javier ;
Bernal-Agustin, Jose L. .
RENEWABLE ENERGY, 2006, 31 (13) :2042-2062
[6]   Predicting the behavior of a grid-connected photovoltaic system from measurements of solar radiation and ambient temperature [J].
Hernandez, J. ;
Gordillo, G. ;
Vallejo, W. .
APPLIED ENERGY, 2013, 104 :527-537
[7]  
International Energy Agency, INT EN AG ANN REP
[8]   Temperature and wind speed impact on the efficiency of PV installations. Experience obtained from outdoor measurements in Greece [J].
Kaldellis, John K. ;
Kapsali, Marina ;
Kavadias, Kosmas A. .
RENEWABLE ENERGY, 2014, 66 :612-624
[9]  
Klein S., 2009, TRNSYS 17 TRANSIENT
[10]   Comparison of measured and predicted long term performance of grid a connected photovoltaic system [J].
Mondol, Jayanta Deb ;
Yohanis, Yigzaw G. ;
Norton, Brian .
ENERGY CONVERSION AND MANAGEMENT, 2007, 48 (04) :1065-1080