Utilization of BIM in Steel Building Projects: A Systematic Literature Review

被引:9
作者
Avendano, Jose Ignacio [1 ]
Zlatanova, Sisi [2 ]
Domingo, Alberto [1 ]
Perez, Pedro [3 ]
Correa, Christian [3 ]
机构
[1] Univ Polytech Valencia, Dept Construct Engn & Civil Engn Projects, Valencia 46003, Spain
[2] Univ New South Wales, Sch Built Environm, GRID, Sydney, NSW 2052, Australia
[3] Univ Catolica Maule, Dept Civil Works, Fac Engn Sci, Talca 3480094, Chile
关键词
building information modeling (BIM); steel project life cycle; project management; communication in steel construction projects; INFORMATION MODELING BIM; GENERATION; KNOWLEDGE; TRACKING; TIME;
D O I
10.3390/buildings12060713
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This research aims to bridge the information gap pertaining to the utilization of building information modeling (BIM) in steel building projects. Therefore, a systematic literature review (SLR) was conducted to synthesize the available uses. This research involved three phases-planning, execution, and reporting-according to the PRISMA guide, which includes the main aspects of identification, screening, and eligibility. As a result of the SLR, it is evident how and where BIM facilitates steel building projects, which were grouped into three different categories according to their main BIM topics. One of the uses that stands out as a common denominator across the different processes is "early integration". Early integration allows for optimization of the design based on existing resources, directly affecting the cost and time of steel building projects in a positive manner.
引用
收藏
页数:18
相关论文
共 87 条
[1]   Framework for construction system selection based on life cycle cost and sustainability assessment [J].
AbouHamad, Mona ;
Abu-Hamd, Metwally .
JOURNAL OF CLEANER PRODUCTION, 2019, 241
[2]   Salvaging building materials in a circular economy: A BIM-based whole-life performance estimator [J].
Akanbi, Lukman A. ;
Oyedele, Lukumon O. ;
Akinade, Olugbenga O. ;
Ajayi, Anuoluwapo O. ;
Delgado, Manuel Davila ;
Bilal, Muhammad ;
Bello, Sururah A. .
RESOURCES CONSERVATION AND RECYCLING, 2018, 129 :175-186
[3]   Swarm nodes for automated steel installation tracking: A case study [J].
Akanmu, Abiola ;
Okoukoni, Festus .
AUTOMATION IN CONSTRUCTION, 2018, 90 :294-302
[4]   Automated verification of 3D manufacturability for steel frame assemblies [J].
An, Shi ;
Martinez, Pablo ;
Al-Hussein, Mohamed ;
Ahmad, Rafiq .
AUTOMATION IN CONSTRUCTION, 2020, 118
[5]  
Andreini D., 2017, BUSINESS MODEL INNOV, V1, P189
[6]  
[Anonymous], 2017, DOING SYSTEMATIC REV
[7]   An analytical method to estimate the total installed cost of structural steel building frames during early design [J].
Barg, Steve ;
Flager, Forest ;
Fischer, Martin .
JOURNAL OF BUILDING ENGINEERING, 2018, 15 :41-50
[8]  
Bartenbach J., 2019, STAHLBAU, V88, P786, DOI [10.1002/stab.201900019, DOI 10.1002/STAB.201900019]
[9]   A BIM-based framework for quantitative assessment of steel structure deconstructability [J].
Basta, Andrew ;
Serror, Mohammed Hassanien ;
Marzouk, Mohamed .
AUTOMATION IN CONSTRUCTION, 2020, 111
[10]   Site logistics planning and control for engineer-to-order prefabricated building systems using BIM 4D modeling [J].
Bortolini, Rafaela ;
Formoso, Carlos Torres ;
Viana, Daniela D. .
AUTOMATION IN CONSTRUCTION, 2019, 98 :248-264