摘要
Since the 31st of January 2008, ITER is a nuclear operator according to the article 7 of chapter H of the Decree of the 2nd of November 2007 which has follow the law "no 2006-686 relative aux installations nucleaires de base et au controle, en matiere de surete nucleaire, du transport de substances radioactives", the so-called "Transparency Law, TSN law": At this date ITER Organization has sent out the request for Authorization of Creation of the ITER Nuclear Basic Installation (INB), "Demande d'Autorisation de Creation, DAC". The licensing process of an INB follows the French regulation which is a mostly non prescriptive approach based on a continuous dialogue between the nuclear installation owner and the Nuclear Safety Authority, "Autorite de Surete Nucleaire, ASN". This dialogue is based in particular on the writing and the analysis of more and more detailed safety documents, reflecting the progress in the definition and the construction of the project. Steps that will be followed in the licensing process from the present design phase to the dismantling are described in this paper.
引用
收藏
页码:809 / 813
页数:5
相关论文
共 8 条
  • [1] ALEJALDRE C, 2008, 22 IAEA FUS EN C 13
  • [2] Gulden W., 2008, EUROPEAN CONTRIBUTIO
  • [3] *ITER CEA DSM DRFC, 2002, DOSS OPT SUR
  • [4] IZQUIERDO J, 2008, 22 IAEA FUS EN C 13
  • [5] LOUGHLIN MJ, 2008, ITER NUCL ANAL STRAT
  • [6] REYES S, 2008, UPDATED MODELLING PO
  • [7] Progress in licensing ITER in cadarache
    Rodríguez-Rodrigo, L
    Girard, JP
    Uzan-Elbez, J
    Marbach, G
    Garin, P
    Rosanvallon, S
    [J]. FUSION ENGINEERING AND DESIGN, 2005, 75-79 : 1091 - 1095
  • [8] TAYLOR N, 2008, PRELIMINARY SAFETY A