Optimizing the Scheduling of Repetitive Construction to Minimize Interruption Cost

被引:43
作者
Altuwaim, Ayman [1 ,2 ]
El-Rayes, Khaled [1 ]
机构
[1] Univ Illinois, Dept Civil & Environm Engn, Urbana, IL 61801 USA
[2] King Saud Univ, Dept Civil Engn, Riyadh, Saudi Arabia
关键词
Repetitive construction; Linear scheduling; Resource-driven scheduling; Optimization; Genetic algorithms; Construction management; GA OPTIMIZATION MODEL; LINEAR PROJECTS; CPM/LOB; CPM;
D O I
10.1061/(ASCE)CO.1943-7862.0001510
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper presents the development of a novel optimization model for the scheduling of repetitive construction projects. The model provides original and unique capabilities that enable planners to search for and identify an optimal/near optimal schedule that simultaneously minimizes project duration, crew work interruptions, and interruption costs. The model computations are organized in four major modules: (1)an optimization module that searches for and identifies a near optimal schedule that simultaneously minimizes the project duration, work interruptions, and interruption costs; (2)an initial scheduling module that calculates the early start date and work-continuity total float for each activity in all of its repetitive sections; (3)an intermediate scheduling module that generates a set of feasible schedules that simultaneously minimize project duration and work interruptions; and (4)an interruption cost module that calculates total interruption cost for each of the generated schedules. An application example of a repetitive construction project is analyzed to evaluate model performance and demonstrate its capabilities in optimizing the scheduling of repetitive construction projects.
引用
收藏
页数:12
相关论文
共 36 条
[1]   Scheduling cost optimization and neural dynamics model for construction [J].
Adeli, H ;
Karim, A .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1997, 123 (04) :450-458
[2]   LOB and CPM Integrated Method for Scheduling Repetitive Projects [J].
Ammar, Mohammad A. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (01) :44-50
[3]   Optimized scheduling and buffering of repetitive construction projects under uncertainty [J].
Bakry, Ibrahim ;
Moselhi, Osama ;
Zayed, Tarek .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2016, 23 (06) :782-800
[4]   Optimized acceleration of repetitive construction projects [J].
Bakry, Ibrahim ;
Moselhi, Osama ;
Zayed, Tarek .
AUTOMATION IN CONSTRUCTION, 2014, 39 :145-151
[5]   Resource Leveling in Line-of-Balance Scheduling [J].
Damci, Atilla ;
Arditi, David ;
Polat, Gul .
COMPUTER-AIDED CIVIL AND INFRASTRUCTURE ENGINEERING, 2013, 28 (09) :679-692
[6]   Multiresource Leveling in Line-of-Balance Scheduling [J].
Damci, Atilla ;
Arditi, David ;
Polat, Gul .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (09) :1108-1116
[7]   CPM/LOB Scheduling Method for Project Deadline Constraint Satisfaction [J].
Dolabi, Hamid Reza Zolfaghar ;
Afshar, Abbas ;
Abbasnia, Reza .
AUTOMATION IN CONSTRUCTION, 2014, 48 :107-118
[8]   Linear Scheduling Model with Varying Production Rates [J].
Duffy, Gregory A. ;
Oberlender, Garold D. ;
Jeong, David Hyung Seok .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2011, 137 (08) :574-582
[9]   Optimum planning of highway construction under A+B bidding method [J].
El-Rayes, K .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (04) :261-269
[10]   Object-oriented model for repetitive construction scheduling [J].
El-Rayes, K .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (03) :199-205