An approach to solve the minimum expected makespan flow-shop problem subject to breakdowns

被引:26
作者
Alcaide, D [1 ]
Rodriguez-Gonzalez, A [1 ]
Sicilia, J [1 ]
机构
[1] Univ La Laguna, DEIOC, Tenerife 38204, Spain
关键词
scheduling; stochastic scheduling; flow-shops; expected makespan;
D O I
10.1016/S0377-2217(02)00077-2
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Daily, there are multiple situations where machines or workers must execute certain jobs. During a working day it may be that some workers or machines are not available to perform their activities during some time periods. When scheduling models are used in these situations, workers or machines are simply called "machines". and the temporal absences of availability are known as "breakdowns". This paper considers some of these cases studying stochastic scheduling models with several machines to perform activities. Machines are specialized and models are flow-shops where breakdowns are allowed. The paper proposes a general procedure that tries to solve these problems. The proposed approach converts breakdowns scheduling problems into a finite sequence of without-breakdowns problems. Thus, we consider random variables, which measure the length of availability periods and repair times, to study availability intervals of machines. We propose partial feasible schedules in these intervals and combine them to offer a final global solution to optimize the expected makespan. Computational experiences are also reported. (C) 2002 Elsevier Science B.V. All rights reserved.
引用
收藏
页码:384 / 398
页数:15
相关论文
共 18 条
  • [1] [Anonymous], OPSEARCH
  • [2] [Anonymous], 1997, LOCAL SEARCH COMBINA
  • [3] [Anonymous], DETERMINISTIC STOCHA
  • [4] Baker KR., 1974, Introduction to Sequencing and Scheduling
  • [5] Stochastic scheduling on parallel machines subject to random breakdowns to minimize expected costs for earliness and tardy jobs
    Cai, XQ
    Zhou, S
    [J]. OPERATIONS RESEARCH, 1999, 47 (03) : 422 - 437
  • [6] Fabrycky W.J., 1972, IND OPERATIONS RES
  • [7] French S., 1982, Sequencing and Scheduling
  • [8] Grant E., 1996, Statistical Quality Control
  • [9] Johnson Selmer Martin., 1954, NAV RES LOG, V1, P61, DOI [10.1002/nav.3800010110, DOI 10.1002/NAV.3800010110, 10.1002/(ISSN)1931-9193]
  • [10] Lawler E. L., 1993, HDB OPERATIONS RES M, V4