An improved simulated annealing for hybrid flowshops with sequence-dependent setup and transportation times to minimize total completion time and total tardiness

被引:144
作者
Naderi, B. [2 ]
Zandieh, M. [1 ]
Balagh, A. Khaleghi Ghoshe [3 ]
Roshanaei, V. [2 ]
机构
[1] Shahid Beheshti Univ, Dept Ind Management, Management & Accounting Fac, Tehran, Iran
[2] Amir Kabir Univ Technol, Dept Ind Engn, Tehran, Iran
[3] Iran Univ Sci & Technol, Dept Ind Engn, Tehran, Iran
关键词
Scheduling; Hybrid flowshop; Transportation time; Sequence-dependent setup times; Total tardiness; Total completion time; Hybrid simulated annealing; Local search; SHOP SCHEDULING PROBLEMS; FLEXIBLE FLOW LINES; GENETIC ALGORITHM; WEIGHTED TARDINESS; IMMUNE ALGORITHM; M-MACHINE; OPTIMIZATION; HEURISTICS; 2-STAGE; SEARCH;
D O I
10.1016/j.eswa.2008.09.063
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
In this communication, we strive to apply a novel simulated annealing to consider scheduling hybrid flowshop problems to minimize both total completion time and total tardiness. To narrow the gap between the theory and the practice of the hybrid flowshop scheduling, we integrate two realistic and practical assumptions which are sequence-dependent setup and transportation times into our problem. We apply a metaheuristic based on simulated annealing (SA) which strikes a compromise between intensification and diversification mechanisms to augment the competitive performance of our proposed SA. A comprehensive calibration of different parameters and operators are done. We employ Taguchi method to select the optimum parameters with the least possible number of experiments. For the purpose of performance evaluation of our proposed algorithm, we generate a benchmark against which the adaptations of high performing algorithms in the literature are brought into comparison. Moreover, we investigate the impacts of increase of number of jobs on the Performance of our algorithm. The efficiency and effectiveness of our hybrid simulated annealing are inferred from all the computational results obtained in various situations. (C) 2008 Published by Elsevier Ltd.
引用
收藏
页码:9625 / 9633
页数:9
相关论文
共 50 条
[21]   Heuristics and metaheuristics for the mixed no-idle flowshop with sequence-dependent setup times and total tardiness minimisation [J].
Rossi, Fernando Luis ;
Nagano, Marcelo Seido .
SWARM AND EVOLUTIONARY COMPUTATION, 2020, 55
[22]   An Iterated Local Search heuristic for the single machine total weighted tardiness scheduling problem with sequence-dependent setup times [J].
Subramanian, Anand ;
Battarra, Maria ;
Potts, Chris N. .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2014, 52 (09) :2729-2742
[23]   A simulated annealing algorithm approach to hybrid flow shop scheduling with sequence-dependent setup times [J].
H. S. Mirsanei ;
M. Zandieh ;
M. J. Moayed ;
M. R. Khabbazi .
Journal of Intelligent Manufacturing, 2011, 22 :965-978
[24]   Energy-Based Scheduling Optimization To Minimize The Total Energy Consumption And The Total Tardiness In A Single Machine Manufacturing System With The Sequence-Dependent Setup Times [J].
Tarakci, Elif ;
Zaim, Abdul Halim ;
Oztas, Oguzhan .
JOURNAL OF POLYTECHNIC-POLITEKNIK DERGISI, 2024, 27 (01)
[25]   A simulated annealing heuristic for scheduling to minimize mean weighted tardiness in a flowshop with sequence-dependent setup times of jobs - A case study [J].
Parthasarathy, S ;
Rajendran, C .
PRODUCTION PLANNING & CONTROL, 1997, 8 (05) :475-483
[26]   Minimizing makespan in mixed no-wait flowshops with sequence-dependent setup times [J].
Cheng, Chen-Yang ;
Ying, Kuo-Ching ;
Li, Shu-Fen ;
Hsieh, Ya-Chu .
COMPUTERS & INDUSTRIAL ENGINEERING, 2019, 130 :338-347
[27]   Minimising total tardiness for the identical parallel machine scheduling problem with splitting jobs and sequence-dependent setup times [J].
Kim, Jae-Gon ;
Song, Seokwoo ;
Jeong, BongJoo .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2020, 58 (06) :1628-1643
[28]   Constraint based local search for flowshops with sequence-dependent setup times [J].
Riahi, Vahid ;
Newton, M. A. Hakim ;
Sattar, Abdul .
ENGINEERING APPLICATIONS OF ARTIFICIAL INTELLIGENCE, 2021, 102
[29]   An iterated greedy algorithm for the single-machine total weighted tardiness problem with sequence-dependent setup times [J].
Deng, Guanlong ;
Gu, Xingsheng .
INTERNATIONAL JOURNAL OF SYSTEMS SCIENCE, 2014, 45 (03) :351-362
[30]   Scheduling to minimize the sum of weighted flowtime and weighted tardiness of jobs in a flowshop with sequence-dependent setup times [J].
Rajendran, C ;
Ziegler, H .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2003, 149 (03) :513-522