Discrete particle swarm optimization method for the large-scale discrete time-cost trade-off problem

被引:77
作者
Aminbakhsh, Saman [1 ]
Sonmez, Rifat [1 ]
机构
[1] Middle E Tech Univ, Dept Civil Engn, TR-06800 Ankara, Turkey
关键词
Project management; Particle swarm optimization; Discrete time-cost trade-off problem; Construction projects; CONSTRUCTION TIME; GENETIC ALGORITHMS; MANAGEMENT; MODEL;
D O I
10.1016/j.eswa.2015.12.041
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
Despite many research studies have concentrated on designing heuristic and meta-heuristic methods for the discrete time-cost trade-off problem (DTCTP), very little success has been achieved in solving large-scale instances. This paper presents a discrete particle swarm optimization (DPSO) to achieve an effective method for the large-scale DTCTP. The proposed DPSO is based on the novel principles for representation, initialization and position-updating of the particles, and brings several benefits for solving the DTCTP, such as an adequate representation of the discrete search space, and enhanced optimization capabilities due to improved quality of the initial swarm. The computational experiment results reveal that the new method outperforms the state-of-the-art methods, both in terms of the solution quality and computation time, especially for medium and large-scale problems. High quality solutions with minor deviations from the global optima are achieved within seconds, for the first time for instances including up to 630 activities. The main contribution of the proposed particle swarm optimization method is that it provides high quality solutions for the time-cost optimization of large size projects within seconds, and enables optimal planning of real-life-size projects. (C) 2016 Elsevier Ltd. All rights reserved.
引用
收藏
页码:177 / 185
页数:9
相关论文
共 40 条
[1]  
Abdel-Raheem M., 2011, COMPUTING CIVIL ENG, P250
[2]   Nondominated Archiving Multicolony Ant Algorithm in Time-Cost Trade-Off Optimization [J].
Afshar, A. ;
Ziaraty, A. Kasaeian ;
Kaveh, A. ;
Sharifi, F. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2009, 135 (07) :668-674
[3]   Network decomposition-based benchmark results for the discrete time-cost tradeoff problem [J].
Akkan, C ;
Drexl, A ;
Kimms, A .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 165 (02) :339-358
[4]  
Aminbakhsh S., 2013, THESIS MIDDLE E TU A
[5]   Shuffled Frog-Leaping Model for Solving Time-Cost-Resource Optimization Problems in Construction Project Planning [J].
Ashuri, Baabak ;
Tavakolan, Mehdi .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2015, 29 (01)
[6]  
Bettemir O. H., 2009, THESIS MIDDLE E TU A
[7]   Complexity of the discrete time-cost tradeoff problem for project networks [J].
De, P ;
Dunne, EJ ;
Ghosh, JB ;
Wells, CE .
OPERATIONS RESEARCH, 1997, 45 (02) :302-306
[8]   THE DISCRETE TIME-COST TRADEOFF PROBLEM REVISITED [J].
DE, P ;
DUNNE, EJ ;
GHOSH, JB ;
WELLS, CE .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1995, 81 (02) :225-238
[9]  
Demeulemeester E, 1998, J OPER RES SOC, V49, P1153, DOI 10.2307/3010096
[10]  
Eberhart R., 1995, MHS 95 P 6 INT S MIC